Board of Education Regular Business Meeting
School Board Attachment 2025.09.09

Summer 2025 Construction Report.pdf

September 9, 2025 · 3 min read · extracted text · View original

Capital Project Update Progress Report

Summer 2025

Presented by

WEBSTER CENTRAL SCHOOL DISTRICT CAPITAL PROJECT UPDATE SUMMER PROGRESS REPORT TABLE OF CONTENTS CONTRACTOR STATUS​

​

​

​

​

​

​

SECTION 1

PROJECT PHASING SCHEDULE​ ​

​

​

​

​

SECTION 2

PROJECT PHOTOS​ ​

​

​

​

​

​

​

SECTION 3

UP COMING PROJECTS​

​

​

​

​

​

​

SECTION 4

Section 1 Contractor Status

Contractor Status Summary Summer 2025 Schroeder High School Ceiling and Light Replacement This two-year project is now complete. This summer, new ceilings and lights were installed in the first-floor corridors and locker rooms. While the old ceilings were out, contractors also performed abatement on ACM fittings in the corridors and kitchen and replaced dissolving pipe insulation.

Elementary School Roof Replacement The final part of the roofing remediation project is now complete. Elmer Davis restored the 1994 wing at Plank Road North Elementary School, closing out the contract.

Spry Middle School Water Service Repairs Lloyd Mechanical was contracted to replace the water service after an inspection showed the water main was at risk of leaking due to rust. The work is now complete after the installation of a new backflow preventer (RPZ) and the removal of the old exterior one.

Willink Middle School Renovations &Addition A two-year project began in July at Willink Middle School. This summer's work included: ●​ Main Office: New ceilings, lights, flooring, and data drops were installed, and conference room walls were relocated ●​ Staff Bathrooms: A small room on the second floor was converted into two staff bathrooms. ●​ Orchestra Room: A new drop ceiling was installed, integrating the existing suspended sound panels. ●​ OWL Addition: Foundation work has started, with structural steel arriving in September. A temporary wall was built in room D106 to create a new hallway and fire exit.

Schroeder High School Parking Lot ●​ Schroeder Gym Parking Lot: The parking lot reconstruction is complete. Work included new storm drains, a bio retention area, and a larger parking area. New light poles and security cameras will be installed in early September. ●​ Schroeder ADA Access: An ADA ramp was added to Door 33, and push-button ADA operators will be installed at both Door 33 and the Main Entrance.

Section 2 Project Phasing Schedule

WCSD Project Phasing ​ Phase 1​ Schroeder Ceilings and Lights- Completed ​ Elementary Schools Roofing- Completed ​ Spry Middle School Water Service Replacement- Completed ​ Phase 2​ Willink Main office- Completed ​ Willink New Restrooms- Completed ​ Willink Addition- September 2026 ​ Willink Pole Barn- September 2026 ​ Willink Site work- September 2026 ​ Schroeder Parking lot- Completed ​ Phase 3- Scheduled to Start July of 2026 ​ Spry Middle School ​Classroom renovations, Bathroom Renovations, Exterior improvements ​ Thomas High School ​Roof replacement and Remediation, Bathroom Renovations ​Classroom upgrades & Track replacement ​ Willink Middle School ​Roof Remediation ​ Schroeder High School ​Gym Mechanical improvements & Gym Lighting replacement ​ Plank North Elementary School ​Cafeteria Lighting replacement & ADA lift Replacement

​

Section 3

Project Photos

Phase 1A – Schroeder High School Ceiling & Lights

Spry Middle School

Phase 2 – Willink Middle School & Schroeder High School Willink Middle School – OWL Addition

Willink Middle School

Orchestra Room

Willink Middle School

Main Office

Willink Middle School

Staff Bathrooms

Schroeder High School

Parking Lot

Capital Project Update Progress Report Presented by

End of document