Town Board Workshop
Town Board Attachment 2026.04.02

Contingency Use Prposal Package

April 2, 2026 · 2 min read · extracted text · View original

PROPOSED CONTINGENCY USE

PROPOSED ITEMS • Maintenance Shop Heat • HSOW Dumpster Shelter • Aeration Slide Gates • Sludge Pump Spare Parts • Material Matters Consulting Agreement • Primary Clarifier Ice Prevention System 2

MAINTENANCE SHOP HEAT

• The maintenance shop heat was not considered a necessary improvement. • Commissioning of new heating system for Administration building upgrade – shop heating not sufficient • Proposal for new more efficient radiant heating

HSOW DUMPSTER ENCLOSURE ▪ The new HSOW Building will take in hauled-in waste – resulting in screening debris. ▪ Original plan was to haul it down to our Service Building. ▪ Decision to have a dedicated dumpster near the HSOW Building.

AERATION TANK SLIDE GATES o As an early cost cutting exercise, it was determined that the gates were operable, though hard to move. o Decided to not include them in the original budget. o To truly maintain and extend the diffuser’s life, frequent maintenance is needed.

5

SPARE SLUDGE PUMP PARTS ✓ Room in the Solids Building for one pump. ✓ Early decision was to not have spare parts – due to BDP’s service and availability of stock

items. ✓ Current operations – with the Belt Press operational, we understood the need to have a shelf spare in house. 6

MATERIAL MATTERS CONSULTING AGREEMENT ❖Material Matters was part of the original project evaluation ❖Conducted an extensive evaluation of potential outlets for our Class A Fertilizer ❖Brings expertise to a new cost-saving and potential revenue generating endeavor.

7

PRIMARY CLARIFIER ICE PREVENTION SYSTEM ❑ Tanks & equipment were commissioned in the late summer/early fall of 2024. ❑ As temperatures dropped below 20 degrees, we began to have mechanical issues.

❑ Ice build-up on the limit switch and would trip the collector drive. ❑ Installed heat lamps (6) on all collectors. ❑ Numerous extension cords ❑ Safety issue ❑ Potential damage from snow removal 8

CONTINGENCY USE REQUEST ❖ Current Balance of Contingency $988,924.00 ❖ Navitas comfortable with lowering the balance to $500,000.00 with only 4 months left until project completion. ❖ That affords the Town to currently utilize $488,924.00 of the contingency ❖ We are requesting $462,788.00

Contingency Use Item

Cost

Maintenance Shop Heat

$128,620.00

HSOW Dumpster Shelter

$121,384.00

Aeration Slide Gates

$ 59,146.00

Spare Sludge Pump Parts

$ 35,778.00

Material Matters Agreement

$ 51,000.00

Primary Clarifier Ice Prevention

$ 66,860.00

❖ Remaining Contingency Balance $526,136.00

9

QUESTIONS?