Board of Education Regular Business Meeting
School Board Attachment 2025.12.09

BOE 2023 85 Million Phase III Bid Comparison (3).pdf

December 9, 2025 · 2 min read · extracted text · View original

GC Company Base Bid

UDN Construction

HVAC

Plumbing

Electric

Site

Roofing

Pipitone

Thurston Dudek

Billitier

LG Evans

Elmer Davis

$6,476,000

$2,849,500

$978,700

$7,170,000

Alt 1 - Spry Fitness Center & Locker Room

$351,000

$120,100

$102,700

$50,000

Alt 2 - Spry First Floor Ceiling & Lighting

$11,200

$2,200

$56,000

$132,200

$9,000

Alt 3 - Thomas Roof Additional Work Alt 4 - Turf Replacement Option A

$4,067,900

$2,780,422

$623,800 $69,400 $2,182,323 $735,000

$2,323,523 $735,000

Alt 5 - Turf Replacement Option B

$0

Alt 6 - Spry Additional Sidewalk Work

$60,500

Alt 7 - Willink Roof Restoration Work

$60,500 $1,932,255

State Contract Total

Totals $24,322,522

$1,932,255 $0

$6,838,200

$3,104,000

$1,081,400

$7,285,000

$4,863,400

$6,895,000

$30,067,000

GC Contract

Company

Base Bid

UDN Construction

DAgostino

Massa Construction

DiPasquale

$6,476,000

$6,940,000

$6,980,000

$6,615,000

Alt 1

$351,000

$325,000

$250,000

$360,000

Alt 2

$11,200

$41,500

$36,000

$40,000

$6,838,200

$7,306,500

$7,266,000

$7,015,000

Alt 3 Alt 4 Alt 5 Alt 6 Alt 7 Total

UDN Construction

$6,838,200

HVAC Contract

Company

Base Bid

Pipitone

Crosby Brownlie $2,849,500

$3,198,000

Alt 1

$120,100

$148,200

Alt 2

$2,200

$2,400

Alt 3

$132,200

$178,800

$3,104,000

$3,527,400

Alt 4 Alt 5 Alt 6 Alt 7 Total

Pipitone

$3,104,000

Plumbing Contract

Company

Base Bid Alt 1

Lloyd Mechanical

Thurston Dudek

$1,022,480

$978,700

$131,100

$102,700

$1,153,580

$1,081,400

Alt 2 Alt 3 Alt 4 Alt 5 Alt 6 Alt 7 Total

Thurston Dudek

$1,081,400

Electric Contract

Company

Base Bid

Billitier $7,170,000

Alt 1

$50,000

Alt 2

$56,000

Alt 3

$9,000

Alt 4 Alt 5 Alt 6 Alt 7 Total

$7,285,000

Billitier

$7,285,000

Roofing Contract

Company

Base Bid

Elmer Davis

Spring Sheet Metal

Titan

$2,780,422

$3,440,000

$2,967,000

$2,182,323

$2,505,000

$1,498,000

Alternate 7

$1,932,255

$1,966,000

$1,415,000

Total

$6,895,000

$7,911,000

$5,880,000

Alternate 1 Alternate 2 Alternate 3 Alternate 4 Alternate 5 Alternate 6

Elmer Davis

$6,895,000

Site Contract

Company

Base Bid

DiFiore

DiPasquale

Pooler

Villager

LG Evans

Zoldaz

$4,595,000

$5,250,000

$4,306,000

$4,570,000

$4,067,900

$4,879,130

$632,000

$675,000

$621,000

$750,000

$735,000

$630,000

$75,000

$120,000

$62,300

$58,000

$60,500

$60,000

$5,302,000

$6,045,000

$4,989,300

$5,378,000

$4,863,400

$5,569,130

Alternate 1 Alternate 2 Alternate 3 Alternate 4 Alternate 5 Alternate 6 Alternate 7 Total

LG Evans

$4,863,400

End of document