Town Board Meeting
Town Board Attachment 2026.04.02

Proposal package

April 2, 2026 · 42 min read · extracted text · View original
Definition and Use of Contingency

Section 6.4 of the Contract provides for a project contingency and use there of. The provision allows for Navitas to utilize the project contingency for unanticipated costs it has incurred that are not the basis for a Change Order under the Contract Document. Section 6.4.2 (amended in Amendment 3) that any Contingency Savings will be shared with 90% going to Town of Webster and 10% going to Navitas.

Project Status

As of 3/24/26 the project contingency stands at $988,924.

All major systems and pieces of equipment have been mechanically started and all buildings/underground utilities have been installed.

Navitas’ evaluation of project risk has determined that Navitas is comfortable with $500,000 of project contingency to address any remaining risk items before final completion.

Since the unspent contingency funds will ultimately be returned to the Town, Navitas is prepared to permit the Town to utilize $488,924 of project contingency to complete items that are not part of the contract scope by utilizing Navitas subcontractors and agreements within the remaining contractual time of the agreement.

The following potential items have been identified

e Maintenance Shop Heat - $128,620 -The maintenance shop heat was not considered a necessary improvement at the beginning of the contract. Upon commissioning of the new heating system for the administration building it was determined that the shop heating was not sufficient. This scope will replace the heating system for the maintenance shop with a natural gas fired radiant heating system

e HSOW Dumpster Enclosure - $121,384 —- The new HSOW acceptance facility screens debris from septage and grease interceptor waste. The material is collected into tip dumpsters and then transferred to a roll off dumpster for removal and hauling to the landfill. The original design involved transporting the dumpsters to the Service building for placement in the screenings/grit dumpster. It was later determined that a dedicated dumpster near the HSOW facility would be a better location.

e Aeration Slide Gate Install/Plus Upsize Gates $59,146 — During the design of the project the TOW determined thai the slide gates in the aeration basin did not need replacement. During the upgrade of the tanks, the tanks were drained which allowed for a visual inspection of the gates. Upon inspection it was determined that the gates should be replaced.

e Spare Sludge Pump Wet Ends - $35,778 - Limitations on space within the solids building prevent the installation of a spare sludge dewatering feed pump. In order to

eliminate risks from equipment failure the purchase of the spare feed pump provides a shelf spare to allow the plant staff to quickly replace any pump components in the event of failure, removing the risk from supply chain disruptions.

e Material Matters Consulting Agreement - $51,000 - During the design of the system the final use of the fertilizer product had not been determined, therefore a commitment to a consulting agreement to market the material was not deemed prudent. With the options available to the Town it has been determined that marketing the material as a fertilizer with a monetary value is the preferred path and the consulting agreement will support the Town in getting the greatest value for the product.

e Primary Clarifier Ice Prevention System - $66,860 — The primary clarifier gear drives can experience ice build up during extended periods below 20F. The current system of managing ice build up utilizes heat lamps to prevent ice accumulation. An enhanced insulation cover with an integral convection heater provides additional reliability for the system, preventing operator call outs overnight and on weekends. Due to the potential for explosive gases on the surface of the primary clarifiers the system requires explosion proof components.

Total being requested

$462,788.00

since 1884

-@danforth

John W. Danforth Company * 100% Employee Owned

October 3, 2025

Navitas Attn

Justin Poling RE: Webster WWTP

Infrared Heaters JWD Estimate #25-050

PROPOSAL

We are pleased to submit our lump sum quotation including all supervision, labor, materials, and tools required to complete the work for the above-mentioned project, including attached drawings.

Pricing Includes

= Furnish and install o Newgas piping to accommodate the new infrared heaters. See attached drawing. (7) New infrared unit heaters Exhaust venting as recommended by manufacturer Intake venting as recommended from manufacturer Power from existing panels All interconnecting wiring, including but not limited to thermostats. New CO detection and warning systems tied into existing fire alarm system. = One year labor & material warranty from start-up.

oo000

ce

Clarifications:

« Existing unit heaters to remain, as a backup/supplementary source.

« Material being provided is of import and/or domestic manufacture;

» All new ductwork will be provided capped & wrapped; no duct cleaning has been provided for new duct;.

» Mark up on any change work to be 10% Overhead + 5% Profit on any non-subcontracted costs and 10% OH&P on subcontracted costs, regardless of any conflicting language in documents;

» Final contract terms will be negotiated prior to execution, regardless of terms in documents stating otherwise.

Not Included:

New York State sales tax; « ICRA partitions; negative air provisions; risk » Performance bond, payment bond, or special assessmentilife safety requirements; insurances of any kind; = Duct cleaning or passivation of piping « Premium time; Liquidated Damages; M/WBE systems; requirements; workforce % requirements; = Reconditioning/cleaning of owner equipment = Unforeseen conditions or relocation of existing or material; services not explicitly detailed « Any delegated design, design calculations, or =" Concrete, grouting, cut/patch, ceiling work, PE stamp; roofing, structural,painting/coatings, fire = Vibration, seismic, sound, or wind restraints; protection, firestopping, expansion joints, unless depicted on drawings; « Dumpsters and/or environmental remediation = Full time on-site safety rep; (i.e. asbestos, lead, mold, etc.) of any kind; « CAD drawings; BIM coordination and/or * Temporary facilities or temp. equipment, filter gatekeeper of coordination process; changes, IAQ, or equipment maintenance; # Any work that is not explicitly called out in inclusions above.

Page 1 of 3

JOHN W. DANFORTH COMPANY

This scope of work is to be included as part of any contract/PO which results from our proposal for this project.

WE HEREBY PROPOSE TO FURNISH MATERIALS AND LABOR COMPLETE IN ACCORDANCE WITH THE CONDITIONS ABOVE FOR THE SUM OF:

One hundred twenty-eight thousand six hundred twenty and 00/100 dollars....... $ 128,620.00 Payment Terms: Net 30 Days (per NYS Prompt Payment Act)

ACCEPTANCE OF PROPOSAL

The above prices, specifications, and conditions are satisfactory and are hereby accepted. John W. Danforth Company is authorized to do the work as indicated. Payment will be made as outlined above. The conditions of the proposal above stand good for 30 days. Pricing is based on conditions at time of bid. Danforth reserves its right for an adjustment in contract time, price, or both, due to changing conditions relating, but not limited to any pandemic, epidemic, disease outbreak; natural disaster; conflict; or any governmental regulations that are enacted after this date that may impact project cost.

JOHN W. DANFORTH COMPANY

suBmiTTeD BY: Cody R Stevens

Cody R Stevens Design Build Account Executive

AUTHORIZED BY:

Print Customer Name

SIGNATURE:

DATE:

OUR MISSION

DELIVERING INDUSTRY LEADING EXPERIENCES TO OUR CUSTOMERS EVERYDAY.

Page 2 of 3

JOHN W. DANFORTH COMPANY

John W. Danforth Company Terms and Conditions of Sale

Definitions:

Buyer

Entity that purchases goods and/or services be it a contractor, building owner, or other. Seller: Entity to whom Buyer's subcontract/purchase order for goods and/or services is issued to. Manufacturer: Entity that manufactures goods and/or provides services.

Acceptance:

Acceptance of a quotation by the Buyer is also acceptance of all JWD Terms and Conditions of Sale set forth herein. The quotation provided shall be signed and dated by the Buyer where applicable and returned to Seller as proof of acceptance. The processing of the order will commence only upon receipt of the signed accepted quotation. JWD reserves its right to negotiate any contract terms prior to final execution.

Scope of Work

Seller has not accommodated any work beyond what is shown or specifically scoped. Pricing is reliant on assumption that Architect/Engineer has depicted a complete and operable system.

Permanent Equipment for Temporary Heating/Cooling

The permanent systems/equipment are not to be used in any way for temporary heating and/or cooling during construction. If request to use these systems is made by Owner, maintenance and operation of these systems during construction will have an additional cost. Additionally, it will cause the commencement of warranties for these items to go into effect immediately upon their use.

Submittals:

Submittals will be provided only after Purchaser's subcontract/purchase order is received by Seller.

It is assumed that any materials/equipment listed by Engineer as “or equal” will not result in any additional costs or scope modifications for any disciplines (electrical, civil, structural, etc.).

Release for Manufacturing:

All goods that require submittal approval will only be released for manufacturing upon the receipt of written approval and authorization from the Buyer. All goods that require submittal approval prior to releasing for manufacturing will be ordered exactly as shown in the approved submittal unless specifically instructed otherwise in writing by the Buyer.

Payments

Terms of payment are payment in full within thirty (30) days of invoice date unless otherwise authorized in writing by Seller (issuance of contract documents by others is not considered written authorization by Seller).

Pre-fabrication of Materials

Our intent on this project is to pre-fabricate materials that are to be installed on site. During this process fabrication will be pre-built well in advance of physical installation on the jobsite. Any changes made could adversely affect this process, and will be billed accordingly, as appropriate.

Warranties:

Warranties on workmanship, equipment, and controls will commence at the substantial completion of building commissioning and individual system acceptance OR per individual manufacturer's standard warranties; not at substantial completion of the entire overall project (the date of which is driven by the finish work of others, not JWD or its subcontractors). Seller is not responsible for preventative maintenance if equipment is received and intended installation dates are subsequently delayed due to no fault of Seller.

Change Orders

Change order requests shall be in writing from the Buyer. Charges associated with change orders will need to be approved by the Buyer and will be charged to the Buyer.

Duct Sealing & Testing All interior and exterior duct to be sealed per SMACNA Seal Class specified. Duct leakage testing per SMACNA HVAC Air Duct Leakage Test Manual only.

Pipe Pressure Testing Any systems that cannot be easily segmented in large portions (ie: condensate drain, steam humidification, etc.) will be “in service” tested, not a separate pressure test.

Hot Taps, Line-Stopping, and Line Freezing

These complex services come with inherent risk and are performed as an alternative to shutting down/draining systems, for the benefit of Buyer. Due to these inherent risks, Seller does not guarantee successful completion of these procedures. Seller does not guarantee that coupon will be

retained. Seller bears no responsibility for any damages to the system, loss of services, or resultant repairs due to failure of any services. Pricing is based upon typical pipe grade/wall thickness & flow rate velocities. Extra costs related to extraordinary circumstances not defined in the detailed scope of work provided by Seller shall be at Buyer's expense (including, but not limited to, additional cutter sharpening, additional sealing elements, etc

Cancellation of Orders:

Cancellation of orders by Buyer may be subject to a cancellation charge by the Seller or Manufacturer. This will be determined on a case-by-case basis. Any request to cancel a complete or partial order shall be submitted in writing by the Buyer.

Page 3 of 3

TOO'v00'TESZ

Jaquinn 9f044

vLCW

Jaquinn i9ays

NMOHS Sv 3ye25

y20z ANWNYEaS area

880EL AN ‘joodear] Aenpyed Squ0nzaR Eby

“Odd ‘sa1pinBo7 gz uoyeg

g z= p> 3 8 G & s S 9 aod Zi H Be O §¢ 2 $s Uo 25 Sc 482 CS 258 WOU Asa Le I§e OQ sa vu = 1 BS ze & 8 #2 ag < 8 5 Mm oo 2 438 2

SNOISIAY

“NONAWUREW 34 40 HOILEINDS2O

Os 9VE_3N25/

4OOU HONCWHL ONULNAA LNSYEOG MAN - ‘SULVH OFUVUINI MEN OGY

YOON LSul4d - NVId YOOTS TWOIINVHDIW

NIVIN3Y OL ONILSIX3 38 TT¥HS

(—) aN0s LHON NMOHS SLI TOINVHD3N ONY M3N 36 TIVHS (—) GMOS AAV3H NMOHS SIV3LI TYDINVHD3N ‘G3LON 3SIMH3HLO SS31NN_ ‘SBLON 193108

{UNIS 01 WIN DULIOMOUNOAYS

"SQN3931 TVDINVHD3M HOS LOOM O1 ¥3478

“SALON L33HS TWYINID

OL 8

»0-iL = o9L/€ ‘FIWDS ae me) vic 0

we Aq umeig Ses —asat App

Aq paulisaq

BI

Sa aie

ue Hetot

CONSTRUCTION

9/26/2025 Updated 1/13/2026 - per C.W. Navitas, LLC

25618 West 103" Street Olathe, KS 66061

Attn

Justin Poling

Webster WPCF

Change Order Request

HSOW Dumpster Shelter & Pad Cost

BHC can provide the labor, equipment, and material to pour the 12’x 32’ concrete pad and install the dumpster plates, bollards, catch basin, and shed roof structure per the attached detail for the lump sum

price of $438,384.00 $121,384.00

Labor

—$62,430.00— $55,430.00 Materials Inc rebar, dumpster plates conc etc. —$74,454.00- $61,454.00 BHC Fuel & Equipment $4,500.00

Notes:

e Weare proposing to install a 2’x2’x2’ catch basin in the center H20 rated with frame and grate- this is NOT connected to any sewer. e Dumpster plates are per the dryer building roll off dumpster plate detail previously sent

Thank You C.W. Gregory

President

9289 Bonta Bridge Road. Jordan, NY 13080 Tel. (315) 689-6482 Fax (315) 689-1359 www.blue-heron-construction.com

a Gh \

popoou : Buyybi Jo 4amod au ll NN (sapis jseo pue :S8}OU JOUIO [| ‘you ‘Jsem punoue) \ QiNd 8}8JDUOD JOO} | % wy Buipis jeyouuw O \

ish

sjeg|o

| MOUS ¥ SJ9}}NS O X 6 Jeo1dA} ‘spueljog

o* yno duund Jo} .b }S@] UNOS UO ,Z] ‘deop|_/ Fi

,9~ ‘YOUSJ} CUINS |eJ}UdO , G X,} [e4jued e 0} ped adojs O j

ice

189M 0} payoyid joou pays sy9e1} Ja}sdwnp jae}S}+-—%

ich

do}s 18}Ssduunp ‘al} peosyiel O

(usdo uynoS pue jseo) *

YIJOHS J9}OYS Jaysdwing MOSH S|TeM JSO\\ PUe YON uO Buipis jeyow

Zz

LOCATION

Webster WWTP-226 Phillips Road

Date:

9/24/2025

OWNER:

Town of Webster

OWNER P.O. No.:

Comments/Description: Demo existing and replace 6- new influent and effluent SS slide gates - Includes Bulkheading and associated bypassing to install and remove bulkheads. Figuring - 1 week of work per tank - 15 days.

EQUIPMENT QTY RATE PRICE HOURS HOURLY RATES PRICE Example: Per Day LABOR - CL ~d or Reg | OT Base Prem. Fringe Base Prem. Fringe No charge $ - Portio Portion § - $ -__] Example: S - 1§ - Is - S - Project Foreman 15.00 S$ 63.00 S$ 38.00|$ 945.00}$ - S 570.00 S - Laborer 120.00 S$ 32.36 S$ 27.30|$ 3,883.20|$_ - S 3,276.00 S - Iron Worker 120.00 S$ 33.75 S$ 34.01|]$ 4,050.00}$ - S 4,081.20 S - S - Iron Worker 120.00 S$ 33.75 S$ 34.01]$ 4,050.00}$ - S 4,081.20 $ : $- $ -_|[s - |[$ : $ - $ - $ -_|[s - |[$ = $ = $ - $ -_|[s - [$ 2 S - SUBTOTALS $ 12,928.20}$ - S$ 12,008.40 Ss - TOTAL] 375.00 | 0.00 S 24,936.60 S - MATERIAL QTY UNIT UNIT PRICE PRICE S - RW Gates- 6 SS slide gates ea S 10,140.00 | $ 60,840.00 S - [Misc Epoxy & Expendables ea |S 1,800.00 | $ 1,800.00 S - Grout 20 ea S 7.50| $ 150.00 TOTAL | $ - S - MISCELLANEOUS CHARGES PRICE S - s - Bypass Pumps/fuel & BulkHead Material S 2,500.00 S - § - $ : § < § % § - § - s - s - s - TOTAL | $ 2,500.00 iS - SUMMARY $ : Labor - Wages S$ 12,928.20 S - Labor - Fringe $ 12,008.40 iS - Materials S$ 62,790.00 iS - Subtotal - Labor Reg Rate & Materials S$ 87,726.60 $ - OH (applied to RegWage,Fringe & Mtl) 10% S 8,772.66 S - {Profit (applied to RegWage,Fringe, Mtl & O 10% S 9,649.93 TOTAL $ 62,790.00 SUBCONTRACTOR QTY UNIT RATE AMOUNT Labor - Premium Portion of OT S - Ss - Wrkrs Comp (applied to wages only) 15.32% $ 1,980.60 JNYS UI — applied to Wage, OT, Fringe & 12.50% $ 3,364.65 $ FED UI Wrkr Comp) 0.60% iS 161.50 S - Payroll Taxes - FICA 7.65% iS 2,059.17 S % Equipment (no OH&P markup) S - $ - Misc. Charges (no OH&P markup) S$ 2,500.00 S - Subcontractor $ - $ - Subcontractor Mark-Up 15% iS - S - § - TOTAL TOTAL $ "

Charles Gregory Iv , 3

From

Mike Ademovic <MAdemovic@koesterassociates.com>

Sent

Wednesday, September 24, 2025 1:05 PM

To

; Charles'Gregory IV fs.32)

Ce

Kyle Buckles; Gregg Palmer; Matt Rodenhizer

Subject

Re: Webster Additional Aeration Gates

Attachments

Quotation #QT01025020 - Webster, NY - Walter W. Bradley WPCP - Aeration Basin Imprvs.pdf

cw,

lease find attached our quotation for the six (6) stainless steel gates on the referenced project. Our TOTAL SELLING PRICE pricing is: List Price: $60,840 ($10,140 each)

NOTE

We did NOT include any field service.

Regards,

Mike

Q KOESTER

KNOWLEDGEABLE + CARING + LOYAL

Michael Ademovic | Senior Vice President Koester Associates, Inc. 315-790-0561 cell

mademovic@koesterassociates.com

SUPPLYING EQUIPMENT SOLUTIONS & SERVICE FOR WATER & WASTEWATER

RW GATE COMPANY

T-2WAS C= | = 79 102" Street — Suite 100

COMPANY TROY, NEW YORK 12180 OFFICE: 518-874-4750

FAX

518-274-0210 WEBSITE: www.rwgate.com

> - = TBAT i"

QUOTATION

September 19, 2025

To

Blue Heron Construction Quotation #QT01025020

Project

Webster, NY - Walter W. Bradley WPCP - Aeration Basin Improvements Barton & Loguidice

Dear Estimator:

Following is our quotation for the six (6) Stainless Steel Slide Gates on the referenced project. Our offering is as follows:

Item No. 01 - Aeration Basins

Qty. - Size

Six (6) Model RW750-S Slide Gates - 36” wide x 36” tall

Distance from the Invert of the Opening to the Operating Floor: 5.67’ (approx.)

Design Seating Head / Design Unseating Head (invert to MWL): 6’ / 6’

Tag No.:

Dwg No.

see RW Gate Job #24341

Description

The AWWA C561 compliant, self-contained, upward-opening slide gates will be constructed of 304/304L stainless steel with self-adjusting UHMWPE seals along the sides and top and an EPDM flush bottom invert seal. A single, rising, 304 stainless steel operating stem and clear plastic stem cover will be provided.

Operating Mechanism

yoke mounted, manual handwheel-operated gearbox

Mounting Style

Gate frames will be wall surface mounted with 316 stainless steel adhesive anchors and non-shrink grout. Anchor studs, nuts and washers are included.

NOTE

If existing cast iron wall thimbles are present, the installer will need to drill through the flange of the thimble and the concrete behind the flange to install the anchor bolts.

TOTAL SELLING PRICE

$ ($ each)

Quotation #QT01025020 Page 1

GENERAL

Our quotation is based on our best interpretation of the information provided and the description listed herein. Please review the quotation and advise our local representative, Kyle Buckles of Koester Associates at 315-697-3800, if there are any discrepancies between the details on this quotation and the actual requirements. The pricing and deliveries listed in the body of the quotation will be held for 45 days from the date on Page 1.

RW Gate is ISO 9001:2015 certified. RW Gate complies with AIS and Buy American requirements. INCLUDED: Submittal drawings, installation instructions and O&M manuals. Installation instructions will be forwarded with the equipment. Information will be sent electronically unless otherwise indicated by the customer.

EXCLUDED

The following items are specifically excluded; demolition, installation, field measurements, electric actuators, portable operators, wall thimbles, wall pipes, floor sleeves, bulkheads, blind flanges, plugs, concrete, grout, gaskets, mastic, lubricants, grating, handrail, odor

control covers, cover plates, epoxy for anchors and all taxes including local and state sales tax.

PAYMENT

Net 30 days. Please contact RW Gate prior to payment via credit card. An additional charge will be necessary when paying by credit card.

FREIGHT

Full freight to project site is included. Unloading will be the responsibility of others. STANDARD DELIVERY: Submittal drawings will ship within 3-5 weeks of receipt of a purchase order. The gate assemblies will ship 16-20 weeks after receipt of approved submittal drawings. Please contact our local representative for expedited or extended delivery dates.

FIELD SERVICE

Field service is not included. If field service is required, please contact our local

representative for revised pricing. Please provide a 3-week notice for field service.

Best Regards,

Evaw Whippy > - =

Evan Whipps

RW Gate Company ewhipps@rwgate.com

www.RWGATE.com

Quotation #QT01025020 Page 2

RW Gate Pricing \ Download a)

RW Gate Pricing

Charles Gregory |1V<CWG4@blueheroncon.com> D

To

Justin Poling <jpoling@navitas.us.com> Mon 3/23/2026 2:24 PM

Cc

Matt Rodenhizer <Matt.R@blueheroncon.com>

Justin ,

See email below ... New pricing adder will be $13,860 Plus BHC 15% - for a total Adder of $15,939.00. Let me know if you have any questions. | think we only put 15% on it the first time around.

Thanks

From

Mike Ademovic <MAdemovic@koesterassociates.com>

Sent

Thursday, February 26, 2026 3:21:20 PM

To

Charles Gregory IV <CWG4@blueheroncon.com>

Subject

Re: RW Gate Submittal Webster, NY - WPCP Gate Replacement (Blue Heron PO# Webster - 028 , Our SO# 25373)

CW,

Just a follow up to our conversation, we can come down to $74,700. Running the numbers on the slide gate, while it seems like we are adding only a few inches, we are adding 4.4 sqft per gate (36x36 is 9sqft, 42x46 is 13.4sqft).

Regards,

Mike

KOESTER

KNOWLEDGEABLE + CARING » LOYAL

Michael Ademovic | Senior Vice President Koester Associates, Inc.

315-790-0561 cell mademovic@koesterassociates.com

C.W. Gregory IV

Blue Heron Construction O

315-689-6482

F: 315-689-1359

C: 585-730-2967

N it

INAVITOAS PCI Approval Sheet Project Code: WBST3 Date: Dec 07, 2025 Project Name: Town of Webster WRRP Construction PCI #: EXT0136

OCO #: PCI Type: External / Owner Change Orders Description: Aeration Tanks Slide Gates Current Status: Pending;Proceeding APPROVAL Scope Furnish new aeration tank influent and effluent slide tisha Description: gates for tanks 2 through 4. This is for the material ° +. Bx CoS, Eepolrmgnnaaia com OFRas only, labor is excluded. Senior PM: Justin Poling: oe

Owner

BG-m$

' Cost Category Description Amount_Vendor Vendor Name SCO Number 050000.11 EPC_SC _ PIM#36 - Supply & Install Gates - $73,008.00 BHCO 983000 EPC_EC Client Savings -73,008.00 PCI Total: $0.00

NECEIWE

DEC ~8 2025

By ————————

Page

1of 1

Quote

WA\\\ YA Estimate #: 0002259 ex. INDUSTRIES Order Date: 3/24/2026 Customer: Webster, NY Location: 929A

BDP Industries Customer Order Nbr:

PO Box 118

354 State Route 29

Greenwich, NY, 12834

BILL TO

SHIP TO:

Webster, NY 226 Phillips Road

226 Phillips Road Webster NY 14580

Webster NY 14580 United States of America

United States of America

CUSTOMER P.O. NO. TERMS

Net 30 Days NO. ITEM DESCRIPTION QTY. UNIT PRICE TOTAL 1 BN 70-6L / A1-C1-L8- Progressive Cavity Pump, Baseplate Mounted, 15HP, 300GPM @ 30PSI, 1.0000 19,147.2800 19,147.28 FO-GA 310RPM MAX

2 BN 70-6L Progressive Cavity Pump Only 1.0000 12,039.3000 12,039.30 Sales Total: 31,186.58 Freight & Misc.: 0.00 Less Discount: 0.00 Tax Total: 0.00 Total (USD): 31,186.58

Estimate does not include freight, installation or any/all taxes unless otherwise stated. Estimate is in US dollars. 7% Convenience Fee for Credit Card orders.

Pricing valid for 30 days.

PHONE # FAX #

518-695-6851 518-695-5417

brandy@bdpindustries.com

Page

1 of 1

Quote

A A\\\ SD Estimate #: 0002258 ee. INDUSTRIES Order Date: 3/24/2026 Customer: Webster, NY Location: 1667A

BDP Industries Customer Order Nbr:

PO Box 118

354 State Route 29

Greenwich, NY, 12834

BILL TO

SHIP TO:

Webster, NY 226 Phillips Road

226 Phillips Road Webster NY 14580

Webster NY 14580 United States of America

United States of America

CUSTOMER P.O. NO. TERMS

Net 30 Days NO. ITEM DESCRIPTION QTY. UNIT PRICE TOTAL 1 BN 130-6L/A1-C1-L8- Progressive Cavity Pump, 300 GPM Max AT 60 PSI And 175 RPM, Single 1.0000 35,352.4500 35,352.45 FO-GA Mechanical Seal, NORD Gearmotor SK 72FVL - 180MP/4 25HP 460V

2 BN 130-6L Progressive Cavity Pump Only 1.0000 23,738.4000 23,738.40 Sales Total: 59,090.85 Freight & Misc.: 0.00 Less Discount: 0.00 Tax Total: 0.00 Total (USD): 59,090.85

Estimate does not include freight, installation or any/all taxes unless otherwise stated. Estimate is in US dollars. 7% Convenience Fee for Credit Card orders.

Pricing valid for 30 days.

PHONE # FAX # 518-695-6851

518-695-5417

brandy@bdpindustries.com

Page

1 of 1

Arxé™ Material Matters March 4, 2026

Task 1 1.

Town of Webster Biosolids RFP Support

- Support with RFP Development

Participate in an in-person Kickoff Meeting with Webster to tour existing site, understand loading/unloading and on-site storage options, and to discuss various bid / request for information (RFI) options and proposal scoring. Provide an executive summary of meeting decisions and action items.

Identify potential respondents to discuss interest in responding to the RFP, including third-party contractors, farmers identified during previously completed market assessment, and other promising contacts. Review list with Webster.

Contact potential respondents prior to drafting RFP, with interviews focused on timeline, contract duration, guaranteed quantities, and product type(s).

Conduct virtual meeting with Webster to establish/confirm scoring criteria and weighting.

Assist Webster with development of draft solicitation document language and provide feedback on constraints /considerations to solicit the most attractive responses.

Review draft language of solicitation document with Webster and revise as necessary.

Combine Technical and General Requirements with Terms and Conditions and issue draft RFP document to Webster for review and comment.

Organize and participate in a virtual progress meeting with Webster to finalize RFP.

— Bid-Phase Services

Assist Webster with issuance/advertising Final RFP, including contacting Offerors.

Prepare for and participate in pre-proposal meeting and other associated activities; take detailed notes for distribution from site visit.

Support Webster in responding to Offeror questions and/or preparing RFP addendum(s). — Assist with RFP Proposal Review & Scoring

Organize and participate in a virtual progress meeting with Webster to share comments and score proposals and determine the need to engage in interviews.

Assist with bid /proposal review and contractor/customer notification.

Assist Webster in virtual meeting to make final Offeror selection and provide support in contract development, including important contract conditions for Webster to consider.

Estimated Expenses

$1,500 Estimated Effort: $50,000 Total Estimate: $51,500

Page 1 of 1

3/7/2025 1 of 2

PROPOSAL #WG02044 ADD#1 Webster, NY

March 7, 2025

Attn

Rick Kenealy

Town of Webster Sewer Dept 226-A Phillips Rd

Webster NY 14580

Phone

(585) 265-0505

email: rkenealy@ci.webster.ny.us

Re

Webster, NY - Chain Guards & Heater Adder QUOTE DESCRIPTION EXT. PRICE 3 EA LONGITUDINAL HEATER MOUNTING PLATE, 304 SS $ 667.24 3 EA CROSS COLLECTOR HEATER MOUNTING PLATE $ 814.56 é EA ae - HEATER BRACKET, 304 SS (FOR LONG AND § 1,227.03 é EA 10001517-001 - EXPLOSION PROOF ENP PLUG, 125VAC, 15 $ 9851.99 AMPERES, 50-400Hz (FOR LONG AND CROSS) Le LONGITUDINAL INSULATED CHAIN GUARD, 304 SS W/1 INCH ; FOAM BOARD INSULATION $ Aloe CROSS COLLECTOR INSULATED CHAIN GUARD, 304 SS W/1 : is INCH FOAM BOARD INSULATION $ ee 1000101 1-HP-02-21-25 - LIMIT SWITCH BRACKET WITH : ee CONDUIT HOLE, 316 SS $ eee F EA CROSS COLLECTOR CHAIN GUARD EXTENTION MOUNTING § 1,525.13 ANGLES 10001229-010 - NORSEMAN HEATER XB-1 10301T3B11T, 300 WATTS, 120 VOLT, 1 PHASE, 6 EA CONVECTION HEATER, NEMA 7 EXPLOSIONPROOF, BUILT IN THERM. $ | 6,655.09 10000056-002 - ANCHOR SET, 3/8-16 x 4-3/4", 316 SS, a EA (SET=1ATH-1FW-1LW-IHN} (LONG & CROSS) $ os EA 10000342-001 - ADHESIVE ANCHORING SYSTEM, HIT-HY 200-A- § 121.87 V3, FOIL PACK, MIXER & MIXER EXTENSION : 9 EA 10000070-007 - BOLT SET, LOCKNUT, 3/8-16 x 2”, 316 SS, § 19.50 (SET=1BLT-2FW-1LW-1LN) (CROSS ONLY) j TOTAL PRICE: $ 58,595.97 Freight: Factory, Full Freight Allowed to Jobsite Terms: Net 30 Days Engineering Time: 2-4 Weeks Validity: 60 Days Lead Time: 8 Weeks Taxes: Not Included Quoted By: Christopher S. Fredericks

Email

chris.fredericks@brentwoodindustries.com

BRENTWOOD’

Brentwood Industries, Inc. 500 Spring Ridge Dr., Reading PA 19610 Phone: 610.374.5109 brentwoodindustries.com Fax: 610.685.0137

Ui

3/7/2025 2 of 2

VILE LL LL

BRENTWOOD’

Brentwood Industries, Inc. 500 Spring Ridge Dr., Reading PA 19610 Phone: 610.374.5109 brentwoodindustries.com Fax: 610.685.0137

a

WGZ0076200_ WEBSTER WRRF PROJECT, NY INSULATED CHAIN GUARD ASSEMBLY WITH HEATER Summary of Proposed Design:

Brentwood's recommendation for a heated guard solution is to provide new chain guards with foam board insulation added to the interior surfaces, which then reduces the needed sizes of the heaters inside the guards.

The new proposed guard designs incorporate foam board insulation with an insulated bottom/base, with a drive opening cutout, and encompasses the limit switch to reduce airflow into the guard. It is understood from the customer's previous feedback that energy efficiency is important at this plant. The geometry of the guard has been optimized to suit the smallest wattage XP heater feasible (300 W), based on standard theoretical calculations to maintain an internal temperature above freezing at a considered low temperature of -14 degrees F (as Brentwood's research indicated to be a worst case for this site/location).

Below are some images present the design of the new proposed chain guards with heaters.

New Limit Switch Bracket & anchors included to extend bracket/anchors outside of

the guard

i. Overall Plan view of Drive area showing proposed chain guard assembly (Longitudinal Drive Area Shown)

ii. Drive arealSO view . (Longitudinal Drive Area Shown)

iii. Drive area ISO view. (Longitudinal Drive Area Shown)

1.5" Dia. Opening in new limit switch bracket to allow for conduit routing out the backside

Cover to be removed for acess inside the guard

iv. Drive area rear elevation view showing proposed chain guard assembly without cut out for limit switch bracket. (Longitudinal Drive Area Shown)

New Limit Switch Bracket

Guard Design includes neoprene flaps at the drive shaft slot cutout.

Heat Shield

120V, 300W

1" thick foam board

insullation

Heater

Heater Mounting Bracket |

Heat Shield

v. Section taken from Plan view showing location of equipment within the proposed insulated chain guard. Chain guard have heat shield on either side of the heater to reduce heat transferred to the limit switch and guard insulation. (Longitudinal Drive Area Shown)

vi. | Elevation view showing inside of insulated chain guard. (Longitudinal Drive Area Shown)

vii. |View showing bottom base of guard with opening cutout to allow for clearance of the drive chain and tensioner arm. (Longitudinal Drive Area Shown)

New Chain Guard Mounting Extension Angles due to absence of deck/recess

e fe) 0 0 . Esse! ® e .9@ ® :

ab New Limit Switch Bracket & ie © o anchors included to extend bracket/anchors outside of

the guard

viii. | Overall Plan view of Drive area showing proposed chain guard assembly (Cross

Drive Area Shown)

ix. Drive area ISO view (Cross Drive Area Shown).

x. Drive area ISO view (Cross Drive Area Shown).

xi. View showing bottom base of guard with opening cutout to allow for clearance of the drive chain and tensioner arm. (Cross Drive Area Shown).

Convection Heater —- XB

— ie)

Explosion-Proof Natural

Convection Heater

XB

The Norseman™ XB Series convection heater, with ratings up

to 5000 watts, is designed for heating spaces where explosive substances are or may be present. The Norseman™ XB is available with either CSA, or CE ATEX approvals. All units can be fitted with an externally adjustable thermostat.

With the Norseman™ XB, you get a safe and reliable heater with a handsome appearance and state-of-the-art design.

Applications

Typical applications for the Norseman™ XB include:

© Control cabinets and small enclosures e — Storage rooms for paints and cleaners e Grain elevators

e Flour mills

e Spray booths

e Gas plants

e Pump houses

e Marine and offshore

e Oil platforms

¢ — Cleaning and dyeing plants

Selection of Temperature Code

Refer to the atmospheric condition table (Table 2, page 6) at the beginning of this catalog for detailed selection data for the temperature code.

To minimize cost and physical size of the heater, select the heater with the highest temperature code that suits the environment. In Table 8 and Table 9, page 14 a check mark () under the temperature code indicates that the surface temperature of the heater will not exceed the coded value listed in the atmospheric conditions table (Table 2, page 6) at the beginning of this catalog.

Model Coding* - .CSA,,,

XB

4 300 T3B Model Heat Sink Wattage Temperature Code Sotles et Watts x 10 TSB - 329°F (165°C) T8A - 356°F (180°C) 2. bi oo T2D - 215°C (419°F) a T2C - 230°C (46°F) 6 - 25.2 (640)

Construction & Installation

The Norseman™ XB explosion-proof convection heaters utilize Thermon Heating Systems’ unique copper free aluminum extruded convector and patented x-Max® terminal housing. Large convector surface area and high mass fins ensure safe and efficient low temperature heat transfer to the environment. Convectors are black anodized to resist oxidation and maximize heat transfer.

The x-Max® housing can be equipped with multiple tapped conduit entries throughout its length to facilitate installation. A track and trolley system and threaded covers at each end allow easy access to internal components.

All units, except the single heat sink units, have a built-in terminal block for simplified electrical connection.

The Norseman™ XB units are intended for wall or floor mounting with the heater positioned vertically as shown. Dual purpose brackets for floor or wall mounting and wire guards are supplied as standard.

Special Wattage & Lengths

Table 10, page 14 lists the maximum design wattages for the four standard heat sink lengths and configurations.

If standard units listed in Table 8 and Table 9, page 14 do not suit your application, a special unit based on Table 10, page 14 can be supplied (check factory).

3 - 1: T Heater so Phase J. 1 - 120V 1-1Phase T- Thermostat 2 - 208V 3-3Phase R- Moisture-Resistant Design 3 - 240V M- Special Mechanical Features 7 - 480V E- Special Electrical Feature 8 - 600V

H- High Ambient (70°C)

*This nomenclature illustration is intended primarily to explain how a product part number is defined. Not all wattage, size and

temperature code combinations are available. Please consult Table 9, page 14 for availability.

Norseman™

16.125" (410 mm)

Figure 7 — XB Double Unit (XB2)

8.5" (216 mm)

Heat Sink Length Thermostat well JY \ with sensing bulb 3.8125" (97 mm) or 1.25" (32 mm) 4 |<>| 3.5" (89 mm)

Figure 10 — XB Side View Floor Mounting

Figure 8 —-XB Triple Unit (XB3)

Heat Sink

33.875" (860 mm)

Figure 9 —- XB Quadruple Unit (XB4)

———-

8" (205 mm)

Figure 11 — XB Side View Wall Mounting

Table 8 — Norseman™ XB Explosion-Proof Natural Convection Heaters - Standard XB Heaters

| 475 = fefsatalede ‘ (254) | 16.7 750 - [etete t= S| 6||lClUL Se | ae (424) 1000 a baiwlia |e ia | = (694) —_ L . See 1250 - fe Si ele Jail 30 | le (765) 100 Y Viv Vv Vv YY = = = | tee v | | (424) 2000 v vv ANON CS, ao a (594) 3000 v viviviviy 23.4 (594) 3750 v VANES AES VIS AES, ee: (765) 4500 | Y YiVvirvriviv sa a | 7 —_ | | | (765) -

ay XB1-1047T2D fe XB1-6125T2D ga 7 pneihheianil na XB2-4200T2D | XB3-4300T2D XB3-6375T2D | ES | | XB4-6450T20

Norseman™

Jayeo} UONOEAUOD - gX

4 (o>)

Table 9 - Norseman™ XB Explosion-Proof Natural Convection Heaters - Other Models Available

50 }-|-|-|-]-]|- | - | - | 100¢54 | vo vv 1045) | XB1-1005T6 - 100 ee te Yivi-| 1065 | Xeio10T4A 2 of 30.1 (765) | 25 (11.3) XB1-604574A

475 Pee ee ic aes (v= |-| is68 | xei-so4773B8 i 600 vyiviyilyl-|-|- | - | sores | YY = ~~ 75(84.0) ~~ XB3-6060T6 2

750 eS eee 10.0 (254) Sas irri g XB2-1075T2D 800 yvivi[yi[yvl-|- 3017765) i YY ~«100(45.4) = XB4-6080T6 -

850 Zi [eo | 2) eo1tres) — 50 (227) XB2-6085T4A 2 1000 eee ee = = 10.0254) (= | - | - | 3001386) | - XB3-1100T2D 4000 ED re) yo aonen XB2-4100T3B s woo YY vViviv = vi = = 167142) Yo v= | =| 4520.4) — XB3-3100T3B . 1250 Te 30.1 (765) Yo - 75(84.0) ——-XB3-6125T4A 5 1250 3s ese 10.0 (254) =) = | = | 30(13.6) - XB3-1125T2D 1360 Ve Pie gy ee aot vest foe ee Seance) “ XB1-6135T2D 1500 -[-|-|-[-|-[- | - | to0e@sa | [ - = 40(181) = XB4-1150T2D 4500 Vig oly | a Fae e | 284 Gem) SS oes XB3-4150T3B = 1500 MMMMAMAMAMAMAR vo - = 80@27) | xB26150TSB 1600 ee Pe a0 es) Yi v | - } 100454) XB4-6160T4A a 2000 Iviviyv[y]-[- | - | - | 67am | = = |=) 45 @0.4) _ XB3-3200T2D 2250 Ge baa ean Zi |}. bobs XB4-4225T3B S 2250 vivivivivivly || sore | [v| - | - | 75640 | xB3-6225T3B . 2500 Pee | oe ey aon ee ee XB4-3250T2D 2500 Yivy YoY Yo vv) 30:4 (765) = = | = | 5027) . XB2-6250T2D 3000 Pou yey Coy bw 804 ree) Y= = 100/454) -XB4-6300T3B = 3750 vyivivilylylyly ly | 234694 | = = = | 8086.3) - XB4-4375T2D B00 ee ee ee oo ea | . XB4-6500T2D _

Thermostats

Thermon Heating Systems offers a wide variety of explosion-proof thermostats to suit most every need.

All Norseman™ XB series heaters can be fitted with integral line voltage thermostats which are available either externally adjustable or tamper- proof; factory installed or as field installed kit.

Remote thermostat mounting is also available.

Refer to Explosion-Proof Thermostats

XT, page 20 of this Norseman™ catalog when selecting the appropriate thermostat for the desired application.

Accessories

Wire Guards and Baffles

All units are equipped with wire guards.

‘Gull wing’ shaped bright aluminum rear baffles are standard with Norseman™ XB units rated for T2D temperature code (shipped separately).

Convection Heater

XB

a BR

Norseman™

Table 11 — High Ambient Norseman™ XB Explosion-Proof Natural Convection Heaters

50 -)}-)-|-)-) - | - | - | 10005) vioevi vy | 10@85) XB1-1005T4A | 100 boas ae XB1-1010T3C 175 - = = ee = 100054 YY = 1048) XB1-1017T3C | 200 Dy eS Bote | 2 oe tS) XB1-602074A 300 -/|-|-]-|]-|-|- | - | woe |v | - | - | 149 XB1-1030T3 | 400 See le ore | oe XB2-6040T4A | 450 Yo - Yo = Y= Y= 801765) YY = | 25/113) XB1-6045T3C 475 lab OS eee erde) | ee Spee XB1-3047T3 600 viviyly|-|-|- | - | x01) |v |v | v | 75040) XB3-6060T4A | BOO VY Deol ty te le Pe oe ely | 00 ae) XB4-60804A tid 850 Yio- Yo = v= v=) 801765) YY = | 50027) XB2-6085T3C 1000 ee ee iy ay XB2-4100T3 4000 vivilyi[yvyi-[yvl-|- | wre |v | - | - | 4204 XB3-3100T3 oe alah @atirn Ss eas sn 1500 vivivilvl-|yvlyulyv | 2469) |) - | - | eer XB3-4150T3 ie PF aes Eo aT LO pas 1600 vivivilviviyly | - | sormey |v | vw | - | 100654 XB4-6160T3C 2250 Co Fos ei ee osaieoa ye eo oe) XB4-4225T3 250 ~_Yvviviv Yio v 801(7683) Y - = | 75,840) XB3-6225T3 3000 Viviowy ee lew |e solves | le Sl ioodes) XB4-6300T3 Table 12 — High Ambient Norseman™ Maximum Thermostats

Heater Wattages

Thermon Heating Systems offers a wide variety of explosion-proof thermostats to suit most every need.

All Norseman™ XB series heaters can be fitted with integral line voltage thermostats which are available either externally adjustable or tamper- proof; factory installed or as field installed kit.

Remote thermostat mounting is also available.

Refer to Explosion-Proof Thermostats

XT, page 20 of this Norseman™ catalog when selecting the appropriate thermostat for the desired application.

Accessories

Wire Guards

All units are equipped with wire guards.

High Ambient Option

The Norseman™ XB Series heater is now available with a high ambient hazardous location rating up to 70°C. This option is ideal for high ambient chemical storage facilities or gas sampling applications. Refer to Table 11, page 15 for Norsemen™ XB units available in high ambient.

JayeaH UO!}DeAUOD — gX

sare a

Norseman™

Convection Heater

XB

ey Oo

Norseman™ XB Explosion-Proof Natural Convection Heater Standard Features (CE ATEX)

Suitable for the following hazardous location classification: . ae ; e Patented x-Max® housing with slide out terminal block trolley e = EXIl 2G ExdIIC TS or T4 Gb ITS OSATEX13473 (See Table 13, simplifies installation and servicing page 16) e Universal support leg for wall or floor mounting

e — Nickel plated wire guards on all models

e — High surface area black anodized heat emitter with integral tubular heating elements

Table 13 - Norseman™ XB Explosion-Proof Natural Convection Heater Specifications for T3 and T4 Units, Hazardous Location Rating (CE ATEX)

XB1-3040T3B 13 2101 220 XB3-4210T3

6 1 | 6. /XB1-8047T3B 73 2206 230 1 «28.4 (694) 60(27.2) | XB3-423073 6 16.7 (424) 15 (6.8) XB1-3040T3B 13 1 | XB3-4250T3 6 | | XB1-3043T3B TS 1 | | XB3-6252T3 XB1-3047T3B. 73 1 30.1 (765) 75 (34.0) | XB3-6276T3 ae XB2-4084T3B 13 3000 240 1 | XB3-6300T3 7 23.4 (694) 40(181) XB2-4084T3B 13 —«1378 400 3 23.4(694) 60(272) XB3-4138T3B 7 | | XB2-4092T3B 73 1500. ais | 3 | -XB3-415073B. pees XB2-4100T3B | T3 3 xae-6180T38 8 1 | - XB3-4126T3B. 73 "30.1 (765) | 75 (34.0) XB3-6207T3B ay | XB3-4150T3B | 13 XB3-6225T3B 3) 23.4 (694) 60(27.2) XB3-4126T3B 13 | a XB3-4210T3 8 | XB3-4138T3B 73 | 28.4 (694) 60 (27.2) | XB3-420T3 8 | XB3-4150T3B. 13 XB3-4250T3 714 7 cE xB2-6071T4A | T4521 80 | - XB3-6252 71027 30.1 (765) 50 (22.7) XB2-6078T4A 14 | | 80.1 (765) 75 (34.0) | XB3-6276 Peoo | XB2-6085T4A | TA XB3-6300T3 | — aoe ~ —— | __ (2066, et 230 30.1 (765) 75 (34.0) | XB3-6207T3B | 73 (2250 «8 (240 | XB3-622573B 13 Norseman™

End of document