Capital Project Update Progress Report Fall 2025

WEBSTER CENTRAL SCHOOL DISTRICT CAPITAL PROJECT UPDATE FALL PROGRESS REPORT TABLE OF CONTENTS CONTRACTOR STATUS​

SECTION 1

PROJECT PHASING SCHEDULE​

SECTION 2

PROJECT PHOTOS​

SECTION 3

Section 1

Contractor Status

Contractor Status Summary Fall 2025 Phase 1: Closeouts While new phases launched, the team worked to finalize the earliest stages of the Capital Improvement Project. ●​ Roofing: As of October 17th, the district was wrapping up roofing contracts and waiting on final close-out documentation.

Phase 2: Willink Middle School & Schroeder High School By mid-October, Phase 2 projects transitioned from heavy structural work to interior finishes and site-specific coordination. ●​ Willink Addition: o​ The building’s skeleton reached a major milestone with steel and decking completed. Roofing materials were delivered to the site by mid-October to begin enclosing the structure. o​ Interior Renovations: Work in the Willink Main Office was nearly finalized, with only the installation of blinds remaining. Restroom progress was pending the arrival of new doors. ●​ Schroeder Site & Athletics: o​ Additional sitework by Pooler was coordinated to avoid interfering with athletic schedules, specifically holding off on small lot additions until after football playoffs. o​ A change order for the new Shot Put area was officially approved in October.

Phase 3: Spry & Thomas (Bidding & Planning) The focus for Phase 3 during the fall was finalizing budgets and preparing for the competitive bidding process. ●​ Bid Schedule: The bid opening for the Spry and Thomas projects was set for November 3, 2025. ●​ Budget Estimates: Preliminary estimates for this phase totaled over $28 million,

Future Planning The committee used the fall sessions to identify long-term needs for upcoming phases. ●​ WAC Improvements: Future focus areas identified included boiler replacement, pool filtration, pumps, and upgraded badging systems. ●​ Phase 6: Initial discussions took place regarding a potential Phase 6

Section 2

Project Phasing Schedule

WCSD Project Phasing Phase 1Schroeder Ceilings and Lights- Completed Elementary Schools Roofing- Completed Spry Middle School Water Service Replacement- Completed Phase 2Willink Main office- Completed Willink New Restrooms- Completed Willink Addition- September 2026 Willink Pole Barn- September 2026 Willink Site work- September 2026 Schroeder Parking lot- Completed Phase 3 and 4- Scheduled to Start Spring of 2026 Thomas High School ✔​ Roof Replacement and Remediation ✔​ Faculty Bathroom Renovations ✔​ Classroom Upgrades ✔​ Track & Turf Replacement Willink Middle School ✔​ Roof Remediation Spry Middle School ✔​ Classroom Renovations, Bathroom Renovations ✔​ Locker Room and Gym Bleacher Replacement ✔​ Entrance Renovations Schroeder High School - $500,000 Capital Transfer Project ✔​ Gym Mechanical Improvements and Gym Lighting Replacement Plank North Elementary School -100K Capital Outlay ✔​ Cafeteria Lighting Replacement and ADA Lift Replacement Phase 5Scheduled to Start January of 2028

Section 3 Project Photos

Phase 2 – Willink Middle School & Schroeder High School Willink Middle School – OWL Addition

Capital Project Update Progress Report Presented by