WEBSTER CENTRAL SCHOOL DISTRICT CAPITAL PROJECT UPDATE QUARTERLY PROGRESS REPORT TABLE OF CONTENTS CONTRACTOR STATUS

SECTION 1

PROJECT PROGRESS SCHEDULE

SECTION 2

PROJECT PHOTOS

SECTION 3

Section 1

Contractor Status

Contractor Status Summary Schroeder High School Exterior– Phase 2A The track and multi-use fields are complete with the exception of the throwing area. The throwing area is waiting on new sod and is expected to be completed before the start of spring sports. Thomas High School – Phase 2B All the fire doors in corridors are now complete. All site lighting and pole barn work was completed. Parking lots with site light and exterior finishes are now also complete. Contractors are continuing installation of fencing around the ball fields. A new fence was installed along Publisher’s Parkway along with a new entrance sign to help direct traffic at the new entryway. All work inside the building is complete except for a few loose ends. Schroeder High School Interior– Phase 2C In the fall months of 2021 work has continued to progress at Schroeder High School. Renovations have been completed on the Phase 1 bathrooms which accounts for nearly half of the bathrooms throughout the building. Renovations continue in the library with the completion of demolition and the start of framing. As the school year progresses faculty bathrooms throughout the school are being renovated. Elementary Schools – Phase 2D Working through the fall, contractors have wrapped up renovations at the Plank North and Klem North libraries. Window replacement at Plank South is also finished. Contractors have moved right into renovations at the State Road library and the Klem North Faculty lounge. Demolition is complete in both of those spaces and the new walls and finishes are going up. Willink Middle School – Phase 2E During winter break, renovations at Willink library began. At this point demolition is complete and the framing has started. Some minor HVAC work has also begun. Transportation Building – 2F SED gave final approval for the project to begin and move forward.

Section 2

Project Phasing Schedule

What is coming up? Thomas High School o Sports Fields- April 2022 o Faculty Bathroom and Roofing-Summer/Fall 2022 Schroeder High School o Library Renovations- August 2022 o 9 bathrooms- August 2022 o Additional brick repair (outside) Klem North E.S. o Alt. work (ceilings, lights, pegboard, casework)- August 2022 o Main Entrance and Door/Window film- August 2022 o Sitework- June 2021- August 2022 State Road E.S. o Library Renovations- April 2022 o Main Entrance and Door/Window film- Summer 2022 o Alt. work (ceilings, lights, pegboard, casework)- Summer 2022 Klem South E.S. o Library Renovation- Summer 2022 o Main Entrance and Door/Window film- June 2021- August 2022 Schlegel E.S. o Library Renovation- Summer 2022 o Main Entrance and Door/Window film- Summer 2022 o Sitework- June 2021- August 2022 Willink Middle School o Library Renovation- July 2022 o HVAC Upgrades- September 2023 Transportation o Bid Project in December/January timeframe o Site work- expected to start February 2022 o Building addition/ renovation- expected to start April 2022

Section 3

Project Photos

Thomas High School

Tech Wing

Complete

Webster Schroeder Library

Current stage

Plank North Library

Before and After

Klem North Library

Before

Klem North Library

After

Before

After

Before

After

Before

After

Before

After

Dewitt Library

Current

State Road Library

Current Renovations

Willink Library

Current Renovations

Capital Project Update Progress Report Presented by

End of document