Board of Education Organizational and Regular Business Meeting
School Board Attachment 2022.07.05

July 5, 2022 BOE Capital Presentation.pdf

July 5, 2022 · 7 min read · extracted text · View original

Webster Central School District Board of Education Workshop Follow Up July 5, 2022

AGENDA Webster Central School District Board of Education 2022 Workshop Update

Klem North Elementary School

1.

Ranking Review

2.

Highlighted Updates

3.

Review By Building

4.

Around the County

5.

Projected Phasing

6.

Projected Debt Service

7.

Estimated Local Impact

8.

Questions and Discussion

PROJECT HIGHLIGHTS UPDATED 1

Removal of State Road Expansion

2

Addition of Plank North Bus Loop

3

Cost Escalation-Market Conditions

4

Finalized square footage for roofing & HVAC estimates

5

Check, Double Check, Check Again…Generator at State

Schroeder High School ➢ Continued Brick Repair around the building ➢ Interior Renovations ➢ HVAC and Plumbing Improvements ➢ Upgraded emergency generator ➢ Fire safety systems update ➢ Replace turf of existing stadium

➢ Total Cost: $13,489,016

Thomas High School ➢ OWL program expansion ➢ HVAC Upgrades-including A/C for building ➢ Interior Renovations ➢ Fire safety systems update ➢ Replace track and scoreboard ➢ Replace turf at stadium ➢ Total Cost: $32,720,105

Willink Middle School ➢ OWL expansion ➢ Upgrade emergency generator ➢ Reconstruct all parking lots and expansion of front loop

➢ Total Cost: $9,464,246

Spry Middle School ➢ ➢ ➢ ➢ ➢ ➢

HVAC upgrades-A/C for full building Upgrade emergency generator Interior Renovations Restroom reconstruction Fire safety systems update Drainage work

➢ Total Cost: $14,488,446

Schlegel Road ➢ OWL Expansion ➢ HVAC upgrades ➢ Entrance Landscape improvements

➢ Total Cost: $11,055,589

DeWitt Road ➢ HVAC upgrades-A/C for remainder of the building ➢ Upgrade emergency generator ➢ Reconstruction of bus loop and parking lots

➢ Total Cost: $5,073,650

Klem North ➢ HVAC upgrades - A/C for the entire building ➢ Roof replacement ➢ Emergency generator upgrade and replacement ➢ Entrance Landscape improvements ➢ Total Cost: $7,082,745

Klem South ➢ HVAC upgrades - A/C for the Gym ➢ Emergency generator upgrade and replacement ➢ Entrance Landscape improvements

➢ Total Cost: $1,483,613

Plank North ➢ HVAC upgrades - A/C for the entire building ➢ Roof replacement ➢ Interior Renovations ➢ Entrance Landscape improvements ➢ New entrance onto Plank Road

➢ Total Cost: $9,924,356

Plank South ➢ HVAC upgrades - A/C for the Gym ➢ Emergency generator upgrade and replacement ➢ Entrance Landscape improvements ➢ Sidewalk replacement

➢ Total Cost: $2,410,863

State Road ➢ NO expansion, removed, not feasible at this time ➢ HVAC upgrades - A/C for the entire building ➢ Roof replacement ➢ Emergency generator upgrade and replacement ➢ Entrance Landscape improvements ➢ Northeast parking lot replacement ➢ Update sidewalks in bus loop

➢ Total Cost: $7,082,745

Building

Additions

Renovations

Site Work

Totals

Dewitt

$0

$3,742,720

$1,330,930

$5,073,650

Klem North

$0

$6,824,276

$258,469

$7,082,745

Klem South

$0

$1,225,144

$258,469

$1,483,613

Plank North

$0

$7,942,759

$1,981,597

$9,924,356

Plank South

$0

$1,905,780

$505,083

$2,410,863

Schlegel

$10,338,768

$458,352

$258,469

$11,055,589

State

$0

$7,075,164

$732,205

$7,807,369

Spry

$0

$14,273,055

$215,391

$14,488,446

Willink

$5,944,792

$1,292,346

$2,227,108

$9,464,246

Schroeder

$0

$12,402,412

$1,086,605

$13,489,016

Thomas

$14,861,979

$14,576,732

$3,281,394

$32,720,105

Totals

$31,145,539

$71,718,740

$12,135,722

$115,000,000

Prime Work HVAC

$29,713,705

Roofing

$11,358,687

Bathrooms/Plumbing

$5,702,527

Parking Lots/Driveways

$6,001,517

Entrance Recondition

$1,550,815

Field Improvements

$4,583,390

Building Envelope

$5,454,588

Interior Spaces

$8,813,800

Fire & Life Support Systems

$10,675,433

Additions

$31,145,539

Totals

$115,000,000

Plank South Elementary School

A Few Thoughts… ➢ Projection is a very conservative estimate of building aid ○ Still waiting to meet with project manager at SED ➢ Still a few more hurdles to clear with SED on the additions ➢ Assumes 20 years of borrowing on the new builds ➢ Avoiding the maximum cost allowance ceilings through phasing ➢ Three years of short term borrowings Thomas High School

Year

2022 Potential

Budget

Debt %

Building Aid

Local Share

Levy

Local Share

2025 - 2026

$3,500,000

$213,970,651

1.64%

$1,406,230

$2,093,770

$123,968,762

1.69%

2026 - 2027

$5,776,438

$220,389,771

2.62%

$3,195,698

$2,580,740

$126,448,137

2.04%

2027 - 2028

$7,650,638

$227,001,464

3.37%

$5,087,835

$2,562,803

$128,977,100

1.99%

2028 - 2029

$9,202,410

$233,811,508

3.94%

$6,622,332

$2,580,078

$131,556,642

1.96%

2029 - 2030

$9,203,925

$240,825,853

3.82%

$6,622,332

$2,581,593

$134,187,775

1.92%

2030 - 2031

$9,201,980

$248,050,629

3.71%

$6,622,332

$2,579,648

$136,871,530

1.88%

2031 - 2032

$9,636,525

$255,492,148

3.77%

$6,622,332

$3,014,193

$139,608,961

2.16%

2032 - 2033

$9,275,788

$263,156,912

3.52%

$6,622,332

$2,653,456

$142,401,140

1.86%

2033 - 2034

$9,043,693

$271,051,620

3.34%

$6,622,332

$2,421,361

$145,249,163

1.67%

2034 - 2035

$9,725,468

$279,183,168

3.48%

$6,622,332

$3,103,136

$148,154,146

2.09%

2035 - 2036

$9,406,740

$287,558,663

3.27%

$6,622,332

$2,784,408

$151,117,229

1.84%

2036 - 2037

$9,408,523

$296,185,423

3.18%

$6,622,332

$2,786,191

$154,139,573

1.81%

2037 - 2038

$9,418,950

$305,070,986

3.09%

$6,622,332

$2,796,618

$157,222,365

1.78%

2038 - 2039

$9,422,168

$314,223,115

3.00%

$6,622,332

$2,799,836

$160,366,812

1.75%

2039 - 2040

$9,428,003

$323,649,809

2.91%

$6,622,332

$2,805,671

$163,574,148

1.72%

2040 - 2041

$7,630,823

$333,359,303

2.29%

$5,216,102

$2,414,721

$166,845,631

1.45%

2041 - 2042

$5,627,738

$343,360,082

1.64%

$3,426,634

$2,201,104

$170,182,544

1.29%

2042 - 2043

$2,748,563

$353,660,885

0.78%

$1,534,497

$1,214,066

$173,586,195

0.70%

2043 - 2044

$2,730,275

$364,270,711

0.75%

$766,326

$1,963,949

$177,057,919

1.11%

2044 - 2045

$2,463,800

$375,198,832

0.66%

$766,326

$1,697,474

$180,599,077

0.94%

2045 - 2046

$2,339,550

$386,454,797

0.61%

$766,326

$1,573,224

$184,211,059

0.85%

2046 - 2047

$2,336,788

$398,048,441

0.59%

$766,326

$1,570,462

$187,895,280

0.84%

2047 - 2048

$2,340,413

$409,989,895

0.57%

$766,326

$1,574,087

$191,653,186

0.82%

Area Projects Under Development or Recently Passed District

Dewitt Road Elementary School

Project Estimate

Brighton

$65M

Fairport

$56M

Webster

$115M

Penfield

$73M

Pittsford

$50M

W. Irondequoit

$40M

E. Irondequoit

$70M

HF-L

$39-61M

Rush-Henrietta

$50M

Hilton

$35M

Brockport

$100M

Gates-Chili

$36M

Churchville-Chili

$67M

Liverpool

$72M

Orchard Park

$114M

NEXT STEPS | PRE-REFERENDUM Key Pre-Referendum Estimated Milestones Items • Board Receives Part 1 EAF, Issues resolution to act as lead agency under SEQRA 9/22/22 • Part 1 EAF circulated to involved Agencies (30 day comment period)

9/26/22

• Lead Agency comment period ends

10/26/22

• Board receives part 2 & 3 of EAF declares itself Lead Agency and issues a determination of significance (Special Meeting) • Deadline for board to close SEQRA and approve CIP for Vote (Special Meeting) • 45 day period required

10/27/22

11/08/22 11/08/22

• Market Capital Improvement Project to the voting public

10/22-12/22

• REFERENDUM VOTE

12/13/22

QUESTIONS

End of document