Capital Project Update Progress Report Fall 2022

Presented by

WEBSTER CENTRAL SCHOOL DISTRICT CAPITAL PROJECT UPDATE Fall PROGRESS REPORT

TABLE OF CONTENTS CONTRACTOR STATUS

SECTION 1

PROJECT PHASING SCHEDULE

SECTION 2

PROJECT PHOTOS

SECTION 3

Section 1 Contractor Status

Contractor Status Summary Fall 2022 Schroeder High School Interior In the Fall months work has continued to progress at Schroeder High School. Casework has been installed at the Café and IT Center. Carpet and LVT flooring has been completed in all areas in the Library. Fixtures, lighting, and ceiling tile have been installed in remaining bathrooms. Elementary Schools All contractors are working on punch list items and are expected to be complete this winter.

Willink Middle School The Library was completed and turned over for the school's use. A couple items we are waiting on are the digital wallpaper and cushions for the reading nooks. Once the wallpaper is complete a punch list will be issued to complete the work. The mechanical contractor worked on the replacement of the heat pumps in the A wing over the holiday recess.

Transportation Building Through the fall the contractors have been preparing for the installation of the bus Wash. Final work is being completed in the office. Siding, asphalt, and fencing are now complete. All bus lifts have been installed and are working well. Parking lot lighting is complete along with the bus warmer cord reels.

Scoreboard Project For the new board at the Aquatic Center, the structural steel is installed and painted. Electrical conduit, cameras and speakers are also installed. At Schroeder and Thomas, the electrical service and the foundation is ready for the scoreboards to arrive.

Section 2 Project Phasing Schedule

WCSD Project Phasing -

Thomas High School o Tech Wing- Completed o Alt. Work- Completed o Pool- September- Completed o Sports Fields- April 2021- Completed

-

Schroeder High School (P2C) o Locker rooms- Completed o Library Renovations- January 2023 o 9 bathrooms- Winter 2023

-

All 7 playgrounds- Completed

-

Dewitt E.S. o Library Renovations- Completed o Main Entrance and Door/Window- Completed o Alt. work (ceilings, lights, pegboard, casework)- Completed

-

Plank South E.S. o Library Renovation- Completed o Main Entrance and Door/Window film- Completed o Sitework- Summer Completed

-

Plank North E.S. o Library Renovation- Completed o Main Entrance and Door/Window film- Completed o Sitework- Completed

-

Klem North E.S. o Library Renovation- Completed o Alt. work (ceilings, lights, pegboard, casework)- Completed o Main Entrance and Door/Window film- Completed o Sitework- June 2021- Completed

-

State Road E.S. o Library Renovations- Completed o Main Entrance and Door/Window film- Completed o Alt. work (ceilings, lights, pegboard, casework)- Completed

-

Klem South E.S. o Library Renovation- Completed o Main Entrance and Door/Window film- Completed o Sitework- June 2021- Completed

-

Schlegel E.S. o Library Renovation- Completed o Main Entrance and Door/Window film Completed o Sitework- June 2021- Completed

-

Willink Middle School o Library Renovation- December 2022 o HVAC Upgrades- September 2023

-

Scoreboard Project o Schroeder High School- Spring 2023 o Schroeder WAC – February 2023 o Thomas High School- Spring 2023

Section 3 Project Photos

Schroeder High School Project East Wall

West Wall

Library

Elementary Schools Schlegel Elementary School

Schlegel Library

Willink Middle School Project

Transportation Project

Scoreboard Project Webster Aquatic Center