Board of Education Budget Workshop Meeting #3
School Board Attachment 2023.04.11

Capital Project 2023-April Workshop (1).pdf

April 11, 2023 · 7 min read · extracted text · View original

Capital Project Workshop Webster Central School District

April 11, 2023

Agenda ✓ ✓ ✓ ✓

Meet the Team What did we learn? Scope Updates by Building Financials

2

Team Presentation

Dan Andrews Project Manager

Stacy Welch

Gary Huffman

Program Manager

Vice President

LaBella Associates

Campus Construction Management Group

Campus Construction Management Group

Mark Esposito

Ben Maslona

President

Executive Vice President

Campus Construction Management Group

Fiscal Advisors and Marketing

Bill Marquardt Bond Attorney

Trespasz & Marquardt LLP

Dan Pieters Vice

President

Director of Architecture LaBella Associates

Michael Skill

Blaine Cunningham

Neil Flood

Project Associate

Jared Miller

Director of Facilities

Director of Pessimism

Project Manager

LaBella Associates

Webster Central School District

Webster Central School District

Campus Construction Management Group

3

What Did We Learn? STRENGTHS We did a very good job explaining the why!

WEAKNESSES Digital descriptions and clips missed the mark Reliance on social media to get the word out

Traditional avenues for information dissemination Relook at scope items More building/community presentations

OPPORTUNITIES

Voter apathy Tax Impacts THREATS 4

Building Summaries

DeWitt Road Previous ✓ ✓ ✓ ✓

$5,073,650 HVAC Upgrades Generator Parking Lot and Bus Loop Reconstruction

Current $3,019,596 Elevator Upgrade Generator Parking Lot and Bus Loop Reconstruction ✓ Interior Door Replacement w/security film ✓ ✓ ✓ ✓

6

Klem South Previous ✓ ✓ ✓ ✓

$1,483,613 HVAC Upgrades Generator Entrance Landscaping

Current ✓ $1,008,030 ✓ Ceilings & Light Conversion to LED ✓ Interior Door Replacement w/security film

7

Klem North Previous

Current

$7,082,745 HVAC Upgrades Generator Roof Replacement ✓ Entrance Landscaping

✓ $4,088,810 ✓ Elevator Upgrade ✓ Interior Door Replacement w/security film ✓ Roof Replacement

✓ ✓ ✓ ✓

8

Plank North Previous

Current

$9,924,356 HVAC Upgrades Music Wing Roof Replacement Entrance Landscaping ✓ Bus Loop Addition

✓ ✓ ✓ ✓ ✓

✓ ✓ ✓ ✓ ✓

$7,292,522 Music Wing Roof Replacement Bus Loop Addition Interior Door Replacement w/security film

9

Plank South Previous ✓ ✓ ✓ ✓ ✓

$2,410,863 HVAC Upgrades Generator Sidewalk Repair Entrance Landscaping

Current ✓ $1,254,644 ✓ Ceilings & Light Conversion to LED ✓ Interior Door Replacement w/security film ✓ Sidewalk Repair

10

Schlegel Road Previous ✓ ✓ ✓ ✓

$11,055,589 OWL Addition HVAC Upgrades Entrance Landscaping

Current ✓ $2,412,379 ✓ Interior Door Replacement w/security film ✓ Interior Building Work ❏ Flooring, Ceilings, Lighting Upgrades

11

State Road Previous

Current

✓ $7,807,369 ✓ HVAC Upgrades ✓ Generator Roof Replacement Entrance Landscaping Northeast Parking lot ✓ ✓ Reconstruction ✓ Sidewalk reconstruction ✓ ✓ ✓ ✓ ✓ ✓ ✓

$4,783,279 Elevator Upgrade Interior Door Replacement w/security film Roof Replacement Northeast Parking lot reconstruction Sidewalk reconstruction 12

Spry Middle School Previous

Current

$14,488,446 ✓ HVAC Upgrades ✓ Generator ✓ Restroom ✓ Reconstruction ✓ ✓ Interior Spaces (Carpet, Ceilings, Lights,✓ Tile Floor) ✓ Western Field Drainage✓ System ✓ ✓ ✓ ✓ ✓

$12,196,708 ADA Entrance Generator Restroom Reconstruction Interior Spaces (Carpet, Ceilings, Lights, Tile Floor) Interior Door Replacement w/security film Pole Barn-Storage Elevator Upgrade 13

Willink Middle School Previous

Current

$9,464,246 OWL Expansion Generator Parking Lot Reconfiguration ✓ Sidewalk Replacement

✓ $11,321,942 ✓ OWL Expansion ✓ Interior Door Replacement w/security film ✓ Generator ✓ Parking Lot Reconfiguration ✓ Elevator Upgrade ✓ Second floor bathroom ✓ Back entrance ADA ✓ Pole Barn

✓ ✓ ✓ ✓

14

Thomas High School Previous

Current

$32,720,105 ✓ ✓ OWL Expansion ✓ HVAC Upgrades Interior Renovations ✓ ✓ Generator Upgrade Track Replacement ✓ Stadium turf ✓ replacement ✓ ✓ Roof Work ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓

$19,603,655 Lighting Fixtures to LED Upgrade Faculty Restroom Reconstruction Interior Renovations Interior Door Replacement w/security film Generator Upgrade Track Replacement Stadium turf replacement Roof Work

15

Schroeder High School Previous ✓ ✓ ✓ ✓ ✓

$13,489,016 Exterior Brick Work Interior Renovations Generator Upgrade Stadium turf replacement

Current ✓ $16,259,806 ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓

Additional Funding for Exterior Brick Work Interior Renovations Interior Door Replacement w/security film Elevator Upgrade Generator Upgrade Tech Wing Auto Shop Stadium turf replacement Athletic Entrance Parking Lot Reconstruction

16

Summation of Changes Generators ❖

❖

❖

Interior Work

Feedback gave us ❖ a chance to re-prioritize Do we really need them at this time from an operations ❖ perspective at all elementary schools? Funding targeted elsewhere on safety and security

Carbon Footprint

Identified more ❖ items to be done inside the buildings at the classroom level ❖ Identified items that could be removed and purchased through BOCES technology services

First project would have had a budgetary impact on the electrical usage We have added more lighting upgrades which will reduce the District’s energy output

17

What Else Changed? ▸ Project is More “Aidable” ▹ Had to assume conservatively that Schlegel Owl would have a local share impact with no prior SED approval ▸ All the changes in scope are 100% Building Aidable ▸ Closer to debt coming off ▹ Helps keep a consistent capital exemption ■ No rollercoaster for the tax cap ▹ Permanent financing is out more years ▹ 2010/2014 projects will be paid off

18

Total Project $85,000,00 ✓ Not a $ for $ difference from the December Vote - $30 million less ✓ If you remove 2 OWL expansions and HVAC from original project it would be below this proposed amount ✓ However, we have added more interior work as well have updated projected costs for the work we did not remove (those did not go down!) 19

Prime Work

$

%

HVAC

$1,929,903

2.27%

Roofing

$16,424,684

19.32%

Bathrooms/Plumbing

$6,655,416

7.83%

Parking Lots/Driveways

$11,078,283

13.03%

Field Improvements

$4,678,162

5.50%

Building Exterior

$6,746,934

7.94%

Interior Building Spaces

$19,237,001

22.63%

Safety & Security Upgrades

$11,787,887

13.87%

Additions

$6,461,730

7.60%

Totals

$85,000,000

100.00%

Cost Breakdown By Construction Area

20

Breakdown The Local Share Capital Reserve $10,000,000

1

Doesn’t utilize the whole reserve in case 2 of emergencies

Debt Expires Expiring debt from previous projects from 2010/2014 that will be $10,060,000 in additional costs to allocate towards this project

State Aid $64,940,00 3

Ratio of 76.4%

21

Getting to $0 Tax Impact

$85,000,000

Total Cost of the Project

Minus $64,940,000

Total State Aid

Minus $10,000,000

Total Capital Reserve Allocation

= $10,060,000

Remaining Cost Divided Over the Life of the Project

Minus $10,060,000

Expiring Debt

=$0

Tax Impact

22

Roadmap to Vote Part Deux April 11 Workshop

July BOE Update as necessary

August-October Publication and Community Engagements

1

3

5

2

4

6

May Board Adopts the Resolution

August Detail

October 11 Vote Date

Planning and Estimating

23

Thanks! Any questions?