Town Board Meeting
Town Board Attachment 2026.05.21

Budget Information

May 21, 2026 · 1 min read · extracted text · View original

Budget and Bid Results Pre-bid Estimate

Bid Results

• Salt Barn

$1,972,093

$2,124,439

• Truck Washout Building

$1,687,091

$1,472,849

• Incidentals

$ 400,000

$350,000

• Demo Existing Highway Garage

$ 951,308

$830,712

• Paving and Utilities

$1,489,452

$1,380,000

• Construction Contingency TOTAL

$ 350,000 $ 6,849,944

$ 100,000 $6,258,000

• Possible Cost Savings

($2,075,000)

($1,519,663)

$4,774,944

$4,738,337

TOTAL NET

*Items 2,3,5,8 of VE not included.

Highway Facility Replacement Phase I &II Summary New Highway Building / Cliff Jones Phase I Fund Allocations Salt Barn Truck Washout Building Demo Existing Highway Garage Paving and Utilities Construction Contingency Incidentals Identified Cost Savings Total

$ 22,093,902 ($ 900,677) $ 2,124,439 $ 1,472,849 $ 830,712 $ 1,380,000 $ 100,000 $ 350,000 ($ 1,519,663) $ 25,931,562

Approved Bond Amount

$ 28,250,000

Estimated Amount Under Budget

$2,318,438