Webster Town Board
July 27, 2023
A workshop meeting of the Webster Town Board was called to order by Supervisor Flaherty at
6:30 p.m. at the Webster Town Board Meeting Room, 1002 Ridge Road, Webster, New York,
with the following officials present:
Supervisor ................................................................................ Thomas J. Flaherty
Councilman .............................................................................. William G. Abbott
Councilman .......................................................................................John J. Cahill
Councilwoman .......................................................................... Patricia T. Cataldi
Councilwoman ........................................................................... Ginny L. Nguyen
Town Attorney ........................................................................... Charles J. Genese
Deputy Town Clerk........................................................... Ann Marie Champagne
Department Heads Present:
Deputy Commissioner of Public Works-Sewer ................................... Art Petrone
Finance Director ................................................................................. Paul Adams
Also in attendance:
Wastewater Treatment Plant Chief Operator .....................................Rick Kenealy
***
Supervisor Flaherty announced a Public Hearing to consider amending the Bond Resolution for
the Water Pollution Control Facility Asset Renewal Project and Water Resource Recovery
Facility Improvements.
Before I put the gavel down to start the Public Hearing, I just felt that for
the people watching at home live or if they watch this in the future on tape and certainly for the
people in attendance tonight that a couple of things that might help. First, and Charlie [Town
Attorney], I hope you will help me on this from a law standpoint, three weeks ago the Town
Board did a Resolution to advertise this Public Hearing and per the Law it was in the Webster
Herald’s July 12th edition which that was fifteen days ago, no less than ten days no more than
twenty days, to advertise legally such a thing. I also want to make sure anybody who plans on
speaking tonight or at home who has read the published Public Hearing that initially three weeks
ago we had it from $44 million to $90 million. Over the last three weeks through our Bond
Counsel, Charlie [Town Attorney], through Municipal Solutions our Bond Consultant, we have
reduced it down to $81.5 million. Simply said, the items of the collection system, pump station
Vosburg, and all the conveyance pipes and collection pipes were dropped out of this Project to
keep it isolated down to the Sewer Plant and the treatment alone.
Now some rules of engagement on the Public Hearing. When I put the hammer down, we will
open it and then the speakers will be able to take the podium in the order that they have signed in
tonight. I really would hope that we have some acumen from a standpoint why the speaker is at
the podium that anybody in attendance, there would not be any talking or when they are done
any cheering or booing or any of that type of thing. Each speaker will be given a five-minute
maximum up on the podium. I will give a thirty second warning that you are getting close to that
five minutes. Once all the speakers that have signed in have been heard from, I will put the
gavel down and close the Public Hearing. At that point the Board Members can talk about this
235
07-27-23
Webster Town Board
potential Resolution, questions, answers but the public comment period at that time is closed. I
really want to make sure people in attendance understand that. The two Resolutions that are
potentially going to be voted on tonight, one is the 202-b Approval Resolution which in layman
terms, Charlie [Town Attorney], I think is a Resolution that says that the increase is for the
public improvement.
Yes, it is being done by the Town Board. The Town Board is doing it
on its own motion; it is not doing it as a result of petition.
The second one is actual amendatory bonding of the Project from its
current $44 million to $81.5 million. Last but not least, we will get going. If we move on those
two Resolutions tonight and are approved by the Town Board, which by Law has to be two thirds
of the Board for this type of Resolution which when you have a Board of five, a super majority
per se is a four to one or a five nothing vote. At that point, the CFA deadline for grant
applications in New York this year with WIIA and some others was scheduled as July 28th. We
have tried to communicate why the timing of this being Thursday July 27th there probably will
never be a better time to get the attention of the various grant agencies in New York State than
right now with what is going on in Webster. The plan is to apply for three grants; Water Quality
Improvement (WQIP) for the maximum $10 million, Empire State Development (ESD) which is
for $5 million and then the one that is most commensurate with sewer plants and the one that we
got for Phase I a few years ago when we did the $12 million Secondary Clarifier Asset Renewal
Project is the WIIA Grant. The WIIA Grant is very interesting because back when it was
awarded to the Town on Phase I, the $12 million secondary clarifiers, the parameters of that
grant were 25% of the Project with a maximum of $5 million. A couple of years ago WIIA
expanded it from being a twenty-five percent maximum but no cap at $5 million. So, one of the
things that if this is an $81 million bonding proposal, the Project in essence is $81 million, WIIA
can consider us for the max of twenty-five percent at what is essentially $20.5 million. One last
thing on that, last September 9th was the deadline for last year's WIIA Grant application. We
made that grant application. We were not awarded, and it did not really surprise us because it is
the same thing that happened on Phase I. This is often you do not get the award at the first run
because you got to get closer and closer to shovel ready and groundbreaking. A little premature
but you got to get in line for those things. When we applied last September 9th, we had eleven
letters of support from various local politicians, and I will say muckety-mucks. Right now, as
we get ready for tomorrow's deadline, we are at about forty-seven letters of support. Now some
of those letters of support for this Project are coming from Senator Schumer's office, hopefully
Senator Gillibrand's office, Congressman Morelle's office, Adam Bello, some people that we
would not have even approached last year for letters of support because the Project last year did
not have the aspects that are going on in Webster right now where those people of those high
categories would make letters of support. So, I think that is very important to also note. Last but
not least, if these two Resolutions pass tonight, I think both, Charlie [Town Attorney], are
subject to permissive referendum. Without getting into too much detail, the way our government
works, we are a representative republic; the citizens vote for their leadership; they voted for us;
we make five Town Board member vote on things like this. This is a great country. There is a
lever per se for the citizens to rise up and say, you know what we do not like that vote. So, they
can go out and get approximately twelve hundred signatures of Webster residents who are
registered voters within thirty days to essentially say we disagree with that Town Board's
decision. We would like it to go to a Town-wide vote and that is always something that citizens
236
07-27-23
Webster Town Board
[inaudible] for now. They do not happen too often I guess, and really the parameters around we
are better to be vetted through the Board of Elections. I said twelve hundred signatures, I think it
is an equation based on the last gubernatorial election and all that stuff. So, that and I apologize
is a very long preface but I'm hoping that for people watching at home, people watching the tape,
people in the audience tonight, it may affect what they were or were not going to say at the
Public Hearing.
At 6:39 p.m. Supervisor Flaherty opened the Public Hearing.
Good evening, ladies and gentlemen. Thanks for the opportunity to comment
on the Town Sewer Plant situation. I own and operate Maplewood Nursing Home located here
in Webster. I have served for a number of years as advisor to the Board of Webster Economic
Development Alliance. I have also had some appreciation and understanding for the Sewer Plant
situation having served on both former committees that looked at the factors involved in the
possibility of combining the Town and Village Sewer Plants. There have been a variety of
articles and opinion pieces written about this topic. I believe they have been and can be much
more effective in describing some of the technical aspects of this decision than I can so, I will
stay away from that. As we all know this is a very unusual situation. Most towns a long time
ago connected to Pure Waters and got rid of their sewage treatment plants. By doing so they not
only got rid of the headache of owning and running a plant but also paved the way for avoiding a
community growth capacity limitation due to the sewer. I sympathize with our situation in the
unenviable decision we now face, nonetheless a decision is at hand. Webster will be making the
choice between severely limiting its ability to grow the commercial and residential tax base or
accepting a much higher bonding amount to support capacity and anticipated additional revenue
to offset increasing tax bills. In my mind this is not a hard decision. We must take the risk and
move ahead with bonding the increased amount. Although none of our doing, like it or not
Webster is in the sewage treatment business. The simple fact is that being in the sewer business
requires a capacity that is scaled to existing and future needs of a given community. If we have
limited or no capacity, we no longer have community growth opportunities to sell. It not only
affects the actual revenue stream that will come from the Sewer Plant but also affects the ability
to obtain revenue from community growth. Limited sewer capacity means that Webster will not
be able to consider a large slice of industrial and commercial growth moving forward. In the
worst case, it will affect future residential growth as well. Some look at this situation exclusively
as being about the Coca-Cola Company coming to Town and needing this capacity. It is true that
if we vote this expansion down, we lose the fairlife® Project. Beyond this current Project that
has brought the issue to a head there is a lot more at stake here than just the fairlife® Coca-Cola
Project. This latest Project will be the first of many opportunities and challenges ahead as we
deal with potential new uses at the Xerox property and other situations. In conclusion, I am in
favor of upgrading the Webster Sewer Plant capacity. It is said that perfection is the enemy of
success. We will never have all the payback data and information that will make everyone
comfortable. There will always be risk and uncertainty in any business venture including this
one. It is the nature of the beast. I recommend this path for the sake of this pending fairlife®
Project, and more importantly to give the opportunity for our community to be able to entertain
future commercial and residential offsets. Payback of any bonding that would be shouldered
strictly by the existing commercial and residential taxpayers creates a static pool of payers and
thus an ever-increasing hardship for them. I think it is important to make the right choice here
and leave the door open for the future of Webster. Thank you.
237
07-27-23
Webster Town Board
Matt Chatfield, Webster Village Resident: Thank you for the opportunity. I am also the
Executive Director of the Webster 's Economic Development Alliance. I have had the benefit
over the past several years of being educated on the proposed Sewer Treatment Facility and the
proposed Project and the improvements that are going to be made. It has been contemplated for
several years and based upon all the information that I have that has been relayed to me the
improvements are much needed. My perspective is that this Project will not only improve the
performance of the Plant but will also improve the Plant’s ability to support and serve
commercial, industrial and agricultural businesses both within and outside of the Town. The
benefit to that is, by serving businesses outside of the Town it brings/generates additional
revenue to help support and offset some of that debt service. These improvements will make our
Webster Facility unique within our region and not only a great benefit to our citizens but a true
economic development asset to our community. In particular, the future plan’s ability to accept
and treat biosolids will also create a beneficial fertilizer product that will generate revenue and
support our agricultural community. Lastly, the proposed Project and it's anticipated benefits
have already borne fruit with the selection of Webster by Coca-Cola as a future location of its
newest fairlife® Dairy Production Facility. It was because of the proposed improvements that
are a part of this facility that Webster was selected. We are basically selected to be host of this
generational investment of $650 million. It is my opinion that the Town must approve the
bonding associated with this Project to ensure that our community has the infrastructure
available to support future growth and continued prosperity in Webster. Thank you.
Dave Wohlrab, Webster Resident: Before I start let me say that I am in favor of the fairlife®
Coke Project. I have nothing against them, but I have some concerns. The first concern is the
amount of the bond, $81.5 million, to be borne by the taxpayers of the Town of Webster that are
on the Townwide Sewer District. The Village does not pay for any of this. I understand the
Sewer Plant needed upgrades. We started out with a bond for $33 million that was revised
upwards to $44 million and now the Board is asking for $81.5 million, another increase of $37.5
million; $14 million of which is due to the increase in capacity to support the fairlife® Project.
Through past correspondence with the Supervisor, I understand that fairlife® has agreed in
principle to cover this $14 million. Does the Town have anything in writing at this point, any
contract signed, any agreements in place to pay this $14 million? How will fairlife® pay for this
$14 million? Will they pay before the bond is taken out, thereby reducing the cost of the bond?
If I subtract the $14 million from $81.5 million the result is $67.5 million which is $23.5 million
higher than the first provision and $34.5 million higher than the original Bond Resolution, more
than two times that of the original Bond Resolution. How do you explain the second increase of
$23.5 million that is not due to the fairlife® Project? I want to know where is this $23.5 million
going? My second concern is how the Board plans to pay for the bond. Absent to fairlife®
Project the cost to every taxpayer on Webster Sewer System would be well over an additional
$300 a year on top of the present O&M that is approximately $232 a year. The Supervisor in one
of his columns stated that with the fairlife® Project, increase could be held to $70 a year for the
next twenty years or so bringing the total cost to taxpayers to around $300 a year. He is
combining the O&M, which covers operating costs, labor, maintenance, chemicals and other
incidentals with the capital portion of the bill; capital being used to pay for equipment upgrades,
new equipment, etcetera. So, how is this possible? Two primary ways; first to reduction in
operating costs, all well and good, efficiencies in energy and second, the elimination of landfill
costs associated with trucking, saving trucking costs and landfill costs by selling dried sewage as
fertilizer. That portion of the technology is or was somewhere around $11 million in the first
238
07-27-23
Webster Town Board
bond issue. The revenue from the discharge from the fairlife® Project that should properly go
towards O&M and not capital. This is the revenue that is gained from the discharge to the Sewer
System based on the water intake into the Plant. I believe these are dangerous assumptions that
could place taxpayers approximately 16,000 of us on the hook for up to $67.5 million assuming
fairlife® picks up the remainder of the $81.5 million. What if the flow used to calculate sewer
charges for fairlife® does not materialize. I understand they will have a pretreatment system,
what is to say that in the future a portion of that pretreatment will allow reuse of water or
efficiency in the process reduces the demand for water. After some research on the internet, I
found several articles discussing the contaminants that are found in sewage PFOS and PFOAs.
They are the most concerning because they are showing up in dried sewage sold as commercial
fertilizers. Should we be contaminating our farmland and home gardens with these dangerous
and forever chemicals. These chemicals have been banned in the United States, but they are
imported from other countries.
Bill Clicquennoi, Webster Resident: My background here is as a school principal in Greece for
thirty years and to be part of a discussion like you folks are having about whether you build a
school or not. I was there during the time of rapid growth in the community, and these are the
kinds of decisions that were part of our future look that what it was that we were going to have to
provide. The details that have been shared and when I looked at the Webster Herald and read
what was written this last week. Unfortunately, there have been other editorials that are pretty
damning to the community and don't help residents at all. There are several concepts that I think
are most important and one of them is making sure that we are not shortsighted. Whenever we
are going to grow, the only way we can grow is to put something in place as a foundation for
growth to occur. Webster is growing, it will continue to grow. There will be other industries,
manufacturing plants, etcetera. We have lots of land and there is no question that those lands
will be used by industries in the future that will probably draw on the system that may have a
little bit of a margin of surplus from the bond that is proposed. I am in favor of the bond. I am
in favor of your vote to approve. fairlife® is really secondary to the issue because I went on the
tour of the Plant. I do not know how many of you have but it is patched together. Other than the
fact that I could not breathe for three days but it is patched together. I cannot imagine how the
team there is able to manage with how things are placed, the inefficiency of the Project as it
currently exists, and the efficiency aspect alone is definitely required. The revenue that will
come in and the last gentleman spoke about fertilizer and all, there are ways around all of that.
There is no reason to get into that here but there are income streams and taxes and all of the other
benefits that come from valuing an industry in our area. We have done it with others, we can do
it with fairlife® and more importantly we can do it for the residents of the community who
require good service and good equipment to keep that service operating at full steam. Thank
you.
I am the Chair of Webster Citizen Action League, also known as WCAL. I
am representing them tonight. Our organization was formed ten years ago to be the eyes and
ears advocating for Webster residents. We do this by attending all local government meetings
and videotaping them and making them available to Webster residents on our Facebook page and
website. We favor open transparent government and have tried to keep our local leaders
accountable to the people they serve. We know that with all the monies that are being bonded in
the Town at this time, current taxpayers and future taxpayers of Webster will bear the burden.
Because of this, their voices should be heard. Our Town government needs to be very open
239
07-27-23
Webster Town Board
about how the massive fairlife® Project will benefit Webster. In other words, how will this
improve life for us here in Webster? We need much more transparency from our leaders and
how this Project will affect us. With all the risk Webster is taking, what will be the cost and the
benefits to Webster residents? I am talking about all the monies you know you have been
allowing to go out for this and that, and this and that, you know what I am talking about. You
know all the different projects that are going on. You are considering the Hamlet West Webster,
where is the money going to come from? As residents, the people you are serving. As always
residents are free to check out our Facebook page and see what Webster Citizen Action League
is all about. Please email us, which you will find on our Facebook page, if you would like to join
our effort and keep Webster where life is worth living. Thank you.
Supervisor Flaherty closed the Public Hearing at 7:00 p.m.
I have done a lot of research on the Project. Our Sewage Treatment Plant
is sixty some years old at this point. It is beyond repair in a lot of places. We needed Phase I,
we need Phase II. You have to look at the future. Where are we going to be ten or twenty years
from now? Do we have to do another addition? Let us try to get everything accomplished we
can now, and plan for the future in that process.
As Liaison to the Sewer Department, I certainly know the challenges
that they have faced in the past few years, and we all saw photos and video of the challenges that
they face just today. As Councilman Abbott said we are beyond the point where we can really
replace and repair. It is so old that we cannot get parts for it anymore. I really appreciate the
speakers tonight and talking about the future of Webster because that is really what we are
looking at. We are looking at an investment in our Town. I think that it is a very important
Project. I won't shy away from the fact that we have all on this Board lost a little sleep on a night
or two when we have looked at some of these numbers. Believe me, we understand the gravity
of this but as I said, I do think that it is important, and we are making a good investment here.
I understand that this is a colossal project and is an investment for
everyone. I had an opportunity to meet on a zoom meeting with Ana Liss. This may be a little
bit outside of the scope, but I just want to say about COMIDA, Jeff and Scott from Harris Beach
and they explained all the answers. We do not make a decision slightly, we do a lot of research
so that we can get the best solution and terms for our community, for our constituents. This
Project will put Webster back on the map and open the door for future economic and industrial
development. It will be a win-win situation for everyone. We are trying to be transparent as
much as we can. If you have any questions we are here, so, please come and ask. I know that
Supervisor Flaherty would have most of the answers.
But we are transparent enough to tell people when we do not have the
answers.
You are right and that is paramount. There is not a doubt in anyone's mind
on this Board that upgrades to the Sewer Treatment Plant are badly needed. I was out there
today, the ingenuity of the team out there to repair things is incredible. They have old parts that
break, and they keep part of the old parts. That is a situation that this Sewage Treatment Plant is
in and that they deal with on a weekly basis, So, kudos to your team Art and what you have had
to deal with for years now. With respect to the Phase II upgrades, absolutely needed. I work in
240
07-27-23
Webster Town Board
construction, so I see the price escalation in the last two years. It is incredible. We bid a job two
years ago we are still not done with. We did a material cost analysis, some of these materials
have doubled in cost, so I see that end of it. Then fairlife® comes in and we go from $40 million
to $81 million, and people are right to be concerned. How are we going to pay for this, how
involved is fairlife® going to be in this. I have had these questions. I have sat with the
Supervisor, with the Director of Finance just two days ago to talk about these things and there is
so many moving parts right now, but we are at the stage where we need to bond this money
which does not mean we have to spend it, but we need to do this to apply for our grants. I am
completely in favor of doing these bonds because we need to do the repairs and upgrades and
expansion of the Sewage Treatment Plant. This literally happened. I was up there today, and Art
was showing me the auger area that they replaced and repaired the auger. The auger goes
through a pipe like this, and the underneath of the pipe was literally a piece of gum holding it
from leaking. I am not kidding, that is the condition that they have been dealing with for years
because in my mind strategic planning was not done twenty years ago and ten years ago. You
cannot run a Sewage Treatment Plant with so many moving parts and have the knowledge of the
life of a pump or auger and not put money aside because if you do not, you are in a situation that
we are in right now.
I appreciate everybody that spoke tonight, especially the people that have
questions and concerns. I would say three things really quick. One, I want to make sure
everybody understands the last three big projects in Town that had Bonding Resolutions. Back
in 2017 Phase I of the asset renewal of the Sewer Plant got bonded for $12 million. To John's
point, that does not mean you are going to go into debt for $12 million because we got a $3
million WIIA Grant. So, I think we did not end up going into that for $9 million the way it all
worked with the reserves and all that, came in under budget and came in on time. Then about a
year or two ago, we did the $9.5 million bonding of Sandbar Park. I had a lesson taught to me
about Municipal Law. Why are we bonding for $9.5 million when we already got $5 million in
grants. We know we are not going to spend $9.5 million, and I was taught that is the way the
system works. You have to bond it to the estimated total cost of the project, doesn't matter what
kind of funding you have already in the bank in grants. Last but not least, it was in the paper
today or yesterday was that back in February of this year just five months ago, there was a lot of
you know hand wringing and whatever, but I cannot believe this Board that we are going get $28
million for bonding the new Highway Garage. We said at that point, that does not mean we are
going to go into debt for $28 million. Here we are five months out and the Project’s actual
contracts and what we are going to accept next week, we are $5.5 million better than that $28
million. We are already starting from that point. So, we have a track record of these Bonding
Resolutions, which are part of Municipal Law, to move things along and show that we as a Town
Board have skin in the game and show the world that we are serious about moving this Project
along. I think the Town has done a very good job of managing those projects and maximizing
grants. I am going to say it again, I just told you earlier, we are applying for $35 million in
grants on this Project and we will never ever be in a position to have this much attention from the
State to award us the maximum. I will make the other two things very quick. I realize my sin is
verbosity. The only person that said something tonight that hurt me was Laurie Reynolds.
Transparency, transparency, well I really pride myself on over communicating to the community,
trying to find ways to communicate, being transparent. So, I did a little research today, well the
last couple days, I took the last one hundred Webster Heralds; since June of 2021 when the
Village Board, where Laurie lives in the Village, decided to not regionalize with the Town Sewer
241
07-27-23
Webster Town Board
Plant. Since the Village decided to go their separate way, which is their prerogative, there has
been one Village Board Agenda that has been published in the Webster Herald that has
addressed what they are doing on their Sewer Plant. There were sixty-one out of one hundred of
our Board Agendas and Workshops dedicated to this, to the Sewer Plant, not fairlife®, to the
Sewer Plant. I do not know how much more transparent we could be. I do not know how much
more robust you can be than that because today Dave Wohlrab’s point, and we can have fun with
numbers all day long, how did we get from $31 million, which by the way it was $31 million
when Barton & Loguidice stood up there two years ago on a PER [Preliminary Engineering
Report] and they told us at that time in more words or less, your asset renewal, just fixing the
assets, no revenue; a cost of $31 million. We said “wow that is a problem”. We looked into
energy performance contracts and all of a sudden, well if we get that technology that can help
pay for itself and kick off cash flow to cover some of the asset renewal. Now as John said that
the moving target the last two years has been inflation, this and that, and where did we end up at,
we ended up with $38 million asset renewal up from the $31 million, $29 million is technology
and has nothing to do with fairlife®. We have talked about that technology ad nauseam sixtyone out of one hundred meetings. We have proven and shown all of the revenues and the
guarantees that energy performance does. You want to do the $38 million asset renewal and take
the gum off the auger, we can do that; your EDU is going to be $500 no doubt, O&M and capital
however you want to slice and dice it. Now we do the technology and then serendipitously but I
do believe luck is the residue of design, I think Coke picked us because thankfully we had the
foresight two years ago to take a look at energy performance contracts, to take a look at that
technology that could help us offset costs, build revenue, take us out of the risk of landfills that
might be five states away that our sludge hauling at a $500,000 a year right now might go to $3
million. Thankfully we had the foresight to look at that and research it and be the doubting
Thomases and put our fingers in sixty-one out of hundred meetings. Because of that, when
Coca-Cola fairlife® came along and was picking forty different sites from Indiana and
Pennsylvania, they looked and said, and I don't know if you know this or not, but a dairy product
really looks at sewer and they said well wait a minute, you guys are down the road on this
technology thing and we would be two miles away from that. If there is one hundred reasons
why Coke picked us and we have to do a regression equation to weigh what was one of the
biggest reasons they picked us, no doubt it is the sewer and not because we fixed the secondary
clarifiers for $12 million and not because of $38 million of asset renewal, that is not going to do
it for them. So yes, they come along two and a half months ago and say that and we got to run
back and say, hey what do we do, do we just go with the asset renewal of $38 million and the
$29 million of technology which ad nauseam we have shown everybody under the sun
transparency if they have been paying attention. We decided to take a look at how we could do
it. It is $14 million to go from 5 million gallons a day to 7 million. Dave to your question, no
we do not have something in writing that irrefutably says they are paying the $14 million
because Charlie [Town Attorney] and our Bond Counsel at Harris Beach and their Counsel at
Coca-Cola, Barclay Damon, are trying to paper this up so that it is a legal document where we
can get that money because we cannot just give them municipal bonds because that is illegal.
You cannot give a private company your municipal bonds.
[Inaudible]
242
07-27-23
Webster Town Board
Dave you do not get to talk. You know what, if people watch this and say
it is rude, you are done. So, we have vetted this and from that standpoint I asked you about
acumen.
So here we are at $38 million asset renewal, $29 million technology and $14 million to upsize, to
have Coca-Cola. Here we are in an opportunity with almost fifty letters of support, which
heretofore we would get ten, and in the position possibly to get the most grants we will ever be in
a position to. I say that all because it is kind of a no brainer because once we do this there is no
guarantee that Coca-Cola fairlife® ever comes to Town because there is a lot of things that could
happen after this that have nothing to do with this Town Board that could squirrel that deal and I
assure you if it does, then we will back off on the $14 million because they are not coming to
Town. I mean based on the construction time frame and all that, we are not bound to this $81
million with Coca Cola. I mean we want to put ourselves in a position to keep the process going
with them. I apologize, I probably over spoke it. I chased Dave Wohlrab out of the room. One
thing he didn't get a chance to tell you is the guy emails me three times a week and you know
what I do three times a week, I answer him. I share it with the Board. He has said he has never
had a Supervisor that is as responsive to his questions. I just told him out there, Dave you are a
godsend to me because you ask good questions, and you give me the opportunity to give good
answers as best I can. Then I can share it with the Board saying, hey if Dave Wohlrab is asking
these questions maybe constituents are going to talk to you at the doorstep about these, here is
the Q&A for you.
I also just want to add because I think to those who are watching or may
have tuned in after you explained how this Public Hearing would go, that perhaps you did look
rude to Dave but the fact is that a Public Hearing you have an opportunity to speak and once the
Public Hearing is closed, there is not an opportunity for the people who are in attendance to
speak anymore. So that is really where that was from.
***
The Town Board considered the following two (2) Resolutions:
Resolution No. 263: MOTION by Supervisor Flaherty, seconded by Councilman Cahill, to
determine that it is in the public interest to undertake certain improvements to the Town of
Webster Consolidated Sewer District.
WHEREAS, by Resolution No. 259 of 2021 adopted on September 16, 2021, the Town Board of
the Town of Webster, Monroe County, New York (the “Town”), adopted an order determining
that it was in the Town’s public interest to authorize certain improvements to the Town of
Webster Consolidated Sewer District that encompasses the Town of Webster (the “Town”)
exclusive of the Village of Webster (the “District”), such improvements consisting of the Water
Pollution Control Facility Asset Renewal Project and Water Resource Recovery Facility
Improvements, as set forth and described in a certain engineering report as prepared by Barton &
Loguidice (the “Engineer”), dated July 2021, and on file in the office of the Town Clerk (the
“Project”), at an estimated maximum cost of $30,998,000, all in accordance with Section 202-b
of the Town Law; and
243
07-27-23
Webster Town Board
WHEREAS, prior thereto, by Resolution No. 249 of 2021 adopted on September 2, 2021, the
Town Board determined pursuant to the State Environmental Quality Review Act and the
regulations of the Department of Environmental Conservation promulgated thereunder (6
NYCRR Part 617.5(c)) (collectively, “SEQRA”), that the Project constitutes a “Type I” action
under the New York State Environmental Quality Review Act and the regulations promulgated
thereunder (6 NYCRR Part 617.5(c)) (collectively, “SEQRA”) and based on its coordinated
review determined that the Project will result in no significant impacts and, therefore, (a) the
action is not one which “may include the potential for at least one significant adverse
environmental impact”, (b) “there will be no significant adverse environmental impacts”, (c) no
“environmental impact statement” need be prepared, as such quoted terms are defined in
SEQRA, and (d) such determination constitutes a negative declaration for purposes of SEQRA;
and
WHEREAS, by Resolution dated September 16, 2021, the Town Board adopted a bond
resolution authorizing the issuance of up to $30,998,000 in serial bonds of the Town to finance
the Project (the “Original Bond Resolution”); and
WHEREAS, in 2022 the Engineer informed the Town that due to a significant rise in the costs of
materials and labor, the estimated maximum cost of the Project shall need to be increased by
$13,342,000 to a total of $44,340,000, all as is more particularly described in a certain report
prepared by the Engineer entitled “Basis of Design Report – Walter W. Bradley Water Pollution
Phase 2”, dated July 2022, said report being on file and
available for review at the Town Clerk’s Office; and
WHEREAS, by Resolution No. 263 of 2022 adopted on September 8, 2022, immediately
following a public hearing, the Town Board adopted an order determining that it was in the
Town’s public interest to undertake the Project at the increased maximum cost of $44,340,000;
and
WHEREAS, by Resolution No. 264 of 2022, its Amendatory Bond Resolution adopted on
September 8, 2022 (the “2022 Amending Bond Resolution”), the Town Board amended and
restated the Original Bond Resolution in its entirety so as to (i) increase the maximum estimated
cost of the Project from $30,998,000 to $44,340,000; (ii) appropriate said increased amount; (iii)
increase the amount of bonds authorized thereunder to finance the cost of the Project from
$30,998,000 to $44,340,000; and (iv) restated the plan of finance set forth therein; and
WHEREAS, since adoption of the 2022 Amending Resolution, there have been some additional
revisions to the Project and, along with a significant rise in the costs of materials and labor, the
estimated maximum cost of the Project shall need to be increased by $37,160,000 to a total of
$81,500,000, all as is more particularly described in a certain report prepared by Engineer
entitled “Preliminary Engineering Report Addendum #2 – Webster Water Resource Recovery
Facility Improvements Project”, dated June 2023, said report being on file and available for
review at the Town Clerk’s Office; and
244
07-27-23
Webster Town Board
WHEREAS, by Resolution No. 253 of 2023, adopted on July 20, 2023, the Town Board adopted
a SEQR resolution in connection with such additional revisions to the Project and determined
that the Project, as revised, constitutes a “Type I” action under SEQRA, and based on its
coordinated review determined that the Project, as revised, will result in no significant impacts
and, therefore, (a) the action is not one which “may include the potential for at least one
significant adverse environmental impact”, (b) “there will be no significant adverse
environmental impacts”, (c) no “environmental impact statement” need be prepared, as such
quoted terms are defined in SEQRA, and (d) such determination constitutes a negative
declaration for purposes of SEQRA; and
WHEREAS, by Resolution No. 241 of 2023 adopted on July 6, 2023, a public hearing was called
be held on July 27, 2023 at 6:30 p.m. at the Town of Webster Town Board Meeting Room, 1002
Ridge Road, Webster, New York 14580, to consider whether it was in the public interest to
increase the estimated maximum cost of the Project by $37,160,000 to a total of $81,500,000,
and to hear all persons interested in the subject matter thereof; and
WHEREAS, notice of said public hearing certified by the Town Clerk was duly published and
posted as required by law, to wit: a duly certified copy thereof was published in the Webster
Herald, the official newspaper of the Town, on July 12, 2023 and a copy of such notice was
posted on July 12, 2023 on the signboard maintained by the Town Clerk, and on the Town’s
website, pursuant to Town Law Section 30(6); and
WHEREAS, said public hearing was duly held at the time and place set forth in said notice, at
which all persons desiring to be heard were duly heard; and
NOW THEREFORE, THE TOWN BOARD OF THE TOWN OF WEBSTER, MONROE
COUNTY, NEW YORK HEREBY RESOLVES, AS FOLLOWS:
SECTION
1. Based in part upon the evidence given at the aforesaid public hearing, it is hereby
found and determined that it is in the public interest to undertake the Project as hereinabove
described at the estimated maximum cost of $81,500,000. The Town is hereby authorized to
undertake the Project at such estimated maximum cost.
SECTION
2. The Town Clerk is hereby authorized and directed to cause a certified copy of this
resolution to be duly recorded in the Office of the County Clerk, County of Monroe, New York
within ten (10) days after the adoption hereof, in accordance with Section 195 of the Town Law.
SECTION
3. This resolution shall take effect immediately.
Vote on motion:
Supervisor Flaherty .............Aye
Councilman Abbott .......... Aye
Councilman Cahill ..............Aye
Councilwoman Cataldi ..... Aye
Councilwoman Nguyen ......Aye
Motion carried .................. 5-0
***
Resolution No. 264: MOTION by Councilwoman Cataldi, seconded by Councilman Cahill, to
amend and restate the Bond Resolution dated September 16, 2021 as previously amended by a
Resolution dated September 8, 2022 relating to the authorization of the issuance of up to
$81,500,000 in Serial Bonds of the Town to undertake certain improvements to the Town of
Webster Consolidated Sewer District.
245
07-27-23
Webster Town Board
WHEREAS, by Resolution No. 259 of 2021 adopted on September 16, 2021, the Town Board of
the Town of Webster, Monroe County, New York (the “Town”), adopted an order determining
that it was in the Town’s public interest to authorize certain improvements to the Town of
Webster Consolidated Sewer District that encompasses the Town of Webster (the “Town”)
exclusive of the Village of Webster (the “District”), such improvements consisting of the Water
Pollution Control Facility Asset Renewal Project and Water Resource Recovery Facility
Improvements, as set forth and described in a certain engineering report as prepared by Barton &
Loguidice (the “Engineer”), dated July 2021, and on file in the Office of the Town Clerk (the
“Project”), at an estimated maximum cost of $30,998,000, all in accordance with Section 202-b
of the Town Law; and
WHEREAS, prior thereto, by Resolution No. 249 of 2021 adopted on September 2, 2021, the
Town Board determined pursuant to the State Environmental Quality Review Act and the
regulations of the Department of Environmental Conservation promulgated thereunder (6
NYCRR Part 617.5(c)) (collectively, “SEQRA”), that the Project constitutes a “Type I” action
under SEQRA, and based on its coordinated review determined that the Project will result in no
significant impacts and, therefore, (a) the action is not one which “may include the potential for
at least one significant adverse environmental impact”, (b) “there will be no significant adverse
environmental impacts”, (c) no “environmental impact statement” need be prepared, as such
quoted terms are defined in SEQRA, and (d) such determination constitutes a negative
declaration for purposes of SEQRA; and
WHEREAS, on September 16, 2021, at a regular meeting of the Town Board held on such date,
the Town Board adopted a bond resolution authorizing the issuance of $30,998,000 in serial
bonds of the Town to finance the cost of the Project with a maximum cost not to exceed
$30,998,000 (the “Original Bond Resolution”); and
WHEREAS, in 2022 the Engineer informed the Town that due to a significant rise in the costs of
materials and labor, the estimated maximum cost of the Project shall need to be increased, along
with the amount of any serial bonds authorized to be issued in connection therewith, by
$13,342,000 to a total of $44,340,000, all as is more particularly described in a certain report
prepared by Engineer entitled “Basis of Design Report – Walter W. Bradley Water Pollution
Phase 2”, dated July 2022, said report being on file and
available for review at the Town Clerk’s Office; and
WHEREAS, by Resolution No. 263 of 2022 adopted on September 8, 2022, immediately
following a public hearing, the Town Board adopted an order determining that it was in the
Town’s public interest to undertake the Project at the increased maximum cost of $44,340,000;
and
WHEREAS, by Resolution No. 264 of 2022, its Amendatory Bond Resolution adopted on
September 8, 2022 (the “2022 Amending Bond Resolution”), the Town Board amended and
restated the Original Bond Resolution in its entirety so as to (i) increase the maximum estimated
cost of the Project from $30,998,000 to $44,340,000; (ii) appropriate said increased amount; (iii)
increase the amount of bonds authorized thereunder to finance the cost of the Project from
$30,998,000 to $44,340,000; and (iv) restated the plan of finance set forth therein; and
246
07-27-23
Webster Town Board
WHEREAS, since adoption of the 2022 Amending Resolution, there have been some additional
revisions to the Project and, along with a significant rise in the costs of materials and labor, the
estimated maximum cost of the Project shall need to be increased by $37,160,000 to a total of
$81,500,000, all as is more particularly described in a certain report prepared by Engineer
entitled “Preliminary Engineering Report Addendum #2 – Webster Water Resource Recovery
Facility Improvements Project”, dated June 2023, said report being on file and available for
review at the Town Clerk’s Office; and
WHEREAS, by Resolution No. 253 of 2023, adopted on July 20, 2023, the Town Board adopted
a SEQR resolution in connection with such additional revisions to the Project and determined
that the Project, as revised, constitutes a “Type I” action under SEQRA, and based on its
coordinated review determined that the Project, as revised, will result in no significant impacts
and, therefore, (a) the action is not one which “may include the potential for at least one
significant adverse environmental impact”, (b) “there will be no significant adverse
environmental impacts”, (c) no “environmental impact statement” need be prepared, as such
quoted terms are defined in SEQRA, and (d) such determination constitutes a negative
declaration for purposes of SEQRA; and
WHEREAS, on July 27, 2023, immediately following a duly called public hearing held on
July 27, 2023, the Town adopted an order which determined that it was in the Town’s public
interest to undertake the Project at a maximum cost of $81,500,000; and
WHEREAS, the Town Board of the Town now wishes to amend and restate (in its entirety) the
Original Bond Resolution as amended by the 2022 Amending Resolution, for the reasons
identified above, and to make other modifications to the Original Bond Resolution, as may be
consistent with law; and
NOW THEREFORE, THE TOWN BOARD OF THE TOWN OF WEBSTER, MONROE
COUNTY, NEW YORK HEREBY RESOLVES (by the affirmative vote of not less than twothirds of all the members of such body), TO AMEND AND RESTATE THE ORIGINAL
BOND RESOLUTION, IN ITS ENTIRETY TO READ AS FOLLOWS:
BOND RESOLUTION OF THE TOWN BOARD OF THE TOWN OF
WEBSTER, MONROE COUNTY, NEW YORK (THE “TOWN”),
AUTHORIZING THE ISSUANCE OF UP TO $81,500,000 IN SERIAL BONDS
OF THE TOWN TO FINANCE CERTAIN IMPROVEMENTS TO THE TOWN
OF WEBSTER CONSOLIDATED SEWER DISTRICT CONSISTING OF THE
WATER POLLUTION CONTROL FACILITY ASSET RENEWAL PROJECT
AND WATER RESOURCE RECOVERY FACILITY IMPROVEMENTS
THE TOWN BOARD OF THE TOWN OF WEBSTER, MONROE COUNTY, NEW
YORK HEREBY RESOLVES (by the affirmative vote of not less than two-thirds of all the
members of such body), AS FOLLOWS:
SECTION
1. The Town is hereby authorized to issue up to $81,500,000 principal amount of
serial bonds (including, without limitation, statutory installment bonds) pursuant to the
provisions of the Local Finance Law of the State of New York, constituting Chapter 33-a of the
Consolidated Laws of the State of New York (the “Law”) to finance the Project, as hereinabove
described.
247
07-27-23
Webster Town Board
SECTION
2. It is hereby determined that the maximum estimated cost of the aforementioned
specific object or purpose is $81,500,000, said amount is hereby appropriated therefor and the
plan for the financing thereof shall consist of (i) the issuance of up to $81,500,000 in serial bonds
of the Town authorized to be issued pursuant to Section 1 of this resolution, or bond anticipation
notes issued in anticipation of such serial bonds, (ii) the application of any grant monies received
by the Town from the United States of America or the State of New York with respect to the
Project, and (iii) the assessment, levy and collection of assessments upon the benefited properties
within the District; and, to the extent necessary, the levy and collection of taxes on all taxable
real property of the Town to pay the principal of such bonds or notes and the interest thereon as
the same become due and payable.
SECTION
3. It is hereby determined that the period of probable usefulness for the
aforementioned specific object or purpose is forty (40) years, pursuant to subdivision 4 of
paragraph a. of Section 11.00 of the Law.
SECTION
4. The final maturity of the bonds herein authorized to be issued pursuant to Section
1 of this resolution shall be in excess of five (5) years measured from the date of issuance of the
first serial bond or bond anticipation note issued.
SECTION
5. The temporary use of available funds of the Town, not immediately required for
the purpose or purposes for which the same were borrowed, raised or otherwise created, is
hereby authorized pursuant to Section 165.10 of the Law, for the capital purposes described in
this resolution. The Town shall reimburse such expenditures with the proceeds of the bonds or
bond anticipation notes authorized by Section 1 of this resolution. This resolution shall
constitute a declaration of “official intent” to reimburse the expenditures authorized by Section 1
hereof with the proceeds of the bonds and bond anticipation notes authorized herein, as required
by United States Treasury Regulations Section 1.150-2.
SECTION
6. Each of the serial bonds authorized by this resolution and any bond anticipation
notes issued in anticipation of said bonds shall contain the recital of validity prescribed by
Section 52.00 of the Law and said serial bonds and any bond anticipation notes issued in
anticipation of said bonds shall be general obligations of the Town, payable as to both principal
and interest by a general tax upon all the real property within the Town without legal or
constitutional limitation as to rate or amount. The faith and credit of the Town are hereby
irrevocably pledged to the punctual payment of the principal and interest on said serial bonds and
bond anticipation notes and provisions shall be made annually in the budget of the Town by
appropriation for (a) the amortization and redemption of the bonds and bond anticipation notes to
mature in such year and (b) the payment of interest to be due and payable in such year.
SECTION
7. Subject to the provisions of this resolution and of the Law, pursuant to the
provisions of Section 30.00 relative to the authorization of the issuance of bond anticipation
notes or the renewals of said obligations and of Section 21.00, Section 50.00, Section 54.90,
Sections 56.00 through 60.00 and Sections 62.10 and 63.00 of the Law, the powers and duties of
the Town Board relative to authorizing serial bonds and bond anticipation notes and prescribing
terms, form and contents as to the sale and issuance of bonds herein authorized, including
without limitation the determination of whether to issue bonds having substantially level or
declining debt service and all matters relating thereto, and of any bond anticipation notes issued
in anticipation of said bonds, and the renewals of said bond anticipation notes, are hereby
248
07-27-23
Webster Town Board
delegated to the Supervisor of the Town, the chief fiscal officer of the Town (the “Supervisor”).
Further, in connection with bonds and bond anticipation notes issued under the authority of
Section 1 hereof, the power to contract with and sell bonds and bond anticipation notes to the
New York State Environmental Facilities Corporation pursuant to Section 169.00 of the Law and
to approve the terms, form and content of such bonds and bond anticipation notes, consistent
with the provisions of the Law, is hereby delegated to the Town Supervisor. Further, pursuant to
subdivision b. of Section 11.00 of the Law, in the event that bonds to be issued for the object or
purpose authorized by this resolution are combined for sale, pursuant to subdivision c. of Section
57.00 of the Law, with bonds to be issued for one or more objects or purposes authorized by
other resolutions of this Town Board, then the power of the Town Board to determine the
“weighted average period of probable usefulness” (within the meaning of subdivision a. of
Section 11.00 of the Law) for such combined objects or purposes is hereby delegated to the
Supervisor, as the chief fiscal officer of the Town.
SECTION
8. The Town Supervisor is hereby further authorized, at his sole discretion, to
execute a project financing and loan agreement, and any other agreements with the New York
State Department of Environmental Conservation and/or the New York State Environmental
Facilities Corporation, including amendments thereto, and including any instruments (or
amendments thereto) in the effectuation thereof, in order to effect the financing or refinancing of
the specific object or purpose described in Section 1 hereof, or a portion thereof, by a serial
bond, and, or a bond anticipation note issue in the event of the sale of same to the New York
State Environmental Facilities Corporation.
SECTION
9. The Supervisor of the Town is hereby further authorized to take such actions and
execute such documents as may be necessary to ensure the continued status of the interest on the
bonds authorized by this resolution and any notes issued in anticipation thereof, as excludable
from gross income for federal income tax purposes pursuant to Section 103 of the Internal
Revenue Code of 1986, as amended (the “Code”) and to designate the bonds authorized by this
resolution and any notes issued in anticipating thereof, if applicable, as “qualified tax-exempt
obligations” in accordance with Section 265(b)(3)(B)(i) of the Code.
SECTION
10. The Supervisor is further authorized to enter into continuing disclosure
undertakings with or for the benefit of the initial purchaser of the bonds or notes in compliance
with the provisions of Rule 15c2-12, promulgated by the Securities and Exchange Commission
pursuant to the Securities Exchange Act of 1934.
SECTION
11. The intent of this resolution is to give the Supervisor sufficient authority to
execute those applications, agreements and instruments, or to do any similar acts necessary to
affect the issuance of the aforesaid serial bonds or bond anticipation notes without resorting to
further action of this Town Board.
SECTION
12. The validity of the bonds authorized by this resolution and of any bond
anticipation notes issued in anticipation of said bonds may be contested only if:
(a) such obligations are authorized for an object or purpose for which the Town is not
authorized to expend money; or
249
07-27-23
Webster Town Board
(b) the provisions of law which should be complied with at the date of the publication of
such resolution are not substantially complied with, and an action, suit or proceeding
contesting such validity is commenced within twenty (20) days after the date of such
publication; or
(c) such obligations are authorized in violation of the provisions of the Constitution.
SECTION
13. This resolution shall take effect immediately and the Town Clerk is hereby
authorized and directed to cause a copy of this resolution, or a summary thereof, to be published
in full, together with a notice attached in substantially the form as prescribed in Section 81.00 of
the Law, in the official newspaper(s) of the Town for such purpose.
Vote on motion:
Supervisor Flaherty .............Aye
Councilman Abbott .......... Aye
Councilman Cahill ..............Aye
Councilwoman Cataldi ..... Aye
Councilwoman Nguyen ......Aye
Motion carried .................. 5-0
***
There being no further business to come before the Board, the meeting was adjourned at
7:28 p.m.
____________________________________
Ann Marie Champagne, Deputy Town Clerk