WATER RESOURCE RECOVERY PROJECT Project Review

AGENDA ▪ Project Status

▪ Energy Performance Contract Amendment 3 Scope

Summary ▪ Scope Adjustments During Construction ▪ Project Financials

2

PROJECT STATUS ▪ Project underway for about 1 year.

▪ Construction Target Dates ▪ July 2025: Accept Septage & High Strength Organic Waste

(Revenue) ▪ September 2025: Startup of Biosolids Dryer (Operational cost reduction) ▪ September 2025: Ready to accept waste flow from fairlife facility (Revenue)

3

4

5

TOWN OF WEBSTER/NAVITAS ENERGY PERFORMANCE CONTRACT AMENDMENT 3 SCOPE OF WORK ▪ Focused on accepting waste flow from new

industrial customer

▪ 4th Aeration Tank and upgraded aeration system ▪ Anaerobic Digester ▪ All facility systems of the new Dryer Building ▪ Final Sitework and Utilities 6

SCOPE ADJUSTMENTS DURING CONSTRUCTION Scope expansion ($3,830,000) ▪ High strength organic waste

building ▪ Trickling filter required complete demolition ▪ Relocation of overhead electric utility lines ▪ Administration building expansion ▪ Asbestos remediation

Scope savings ($1,098,000) ▪ Design credits ▪ Purchases via state contracts ▪ Winter construction savings ▪ Scope efficiencies

7

PROJECT FINANCIALS

PROJECT FINANCIALS ▪ Revenue Impact ▪ Septage and High Strength Organic Waste acceptance ▪ New wastewater flow from new industrial customer ▪ One time connection fee from new industrial customer ▪ Operational Cost Savings ▪ Dryer reduces biosolids disposal expense ▪ Energy efficient systems reduce utility expense in existing buildings

▪ New Expenses ▪ New industrial customer increases overall treatment expense ▪ New buildings and systems increases utility expense 9

NET PROJECT COST ▪ Navitas’ Authorized Contract: ▪ Amendment 3: ▪ Total Navitas Contract: ▪ Paving (managed by Town)

▪ Other Project Costs ▪ Gross Project Cost ▪ NY State Grant: ▪ Final Net Project Cost

$ 61,979,047 $ 23,348,802 $ 85,327,849 $ 1,400,000 $ 572,151 $ 87,300,000

$(20,000,000) $ 67,300,000 10

SEWER RATES ▪ 2024 sewer rates are currently $296 per EDU ▪ Future rates forecasted to remain stable ▪ Additional dollars will be budgeted, in reserve, to fund

future infrastructure needs of the sanitary system

11

QUESTIONS