Town of Webster 2025 Budget Facts and Comparisons for Wastewater Treatment Services

The following is a comparison of the 2025 budget including the $87.3M wastewater treatment plant capital project versus a projected 2025 budget had the Town chosen to only do the original $31 million asset renewal project. The comparison demonstrates the impact of Coca-Cola/fairlife coming to Webster, the installation of sludge drying technology, and the increased revenue from the ability to accept high strength organic waste.

Description

2025 Budget Results with $87.3 M Phase II Project

Aggregate Sewer O&M and Capital Charge (EDU) Per Household

$252.93

$344.73

Funds Transferred into Sewer Capital Reserve

$540,000*

$0

Aggregate Amount Over (Under) NYS Tax Cap

($5,158)

$1,434,332

*Historically, the Town has been unable to adequately fund the sewer capital reserve, which supports future sewer plant repairs and asset renewal. This is, in-part, due to virtually flat sewer rates. In fact, from 1998 to 2018, the sewer rate ranged between $162.50 and $167.80. Funding the Sewer Capital Reserve in future budgets will save taxpayers for years to come.

2025 Projected Budget Results with $31.0M Asset Renewal Project

Aggregate EDU Cost Per Household

Dollars budgeted for Sewer Capital Reserve

Year-End Sewer Capital Reserve Balance

1990

$213.62

$0

$0

2000

$167.32

$50,000

$0

2010

$162.50

$250,000

$2,384,649

2015

$167.50

$100,000

$1,770,479

2020

$187.28

$0

$1,611,119

Est. 2025

$252.93

$540,000

$1,900,000