TOWN OF WEBSTER VOSBURG PUMP STATION - CAPITAL PROJECT H0229 REVENUE AND EXPENDITURE BUDGET REVENUE / FUNDING Bond Anticipation Notes / Serial Bonds
H0231 Account # H330.05730 - H0229
Total Estimated Revenue / Funding Sources
Amount 6,350,000 6,350,000
Approved to $5,700,000 6/6/24 TB Resolution May revise to $6,350,000
General Construction
H8130.20140 - H0229
2,643,628
Plumbing
H8130.20140 - H0229
72,760
HVAC
H8130.20140 - H0229
342,882
Electrical Controls & Instrumentation
H8130.20140 - H0229
1,322,953
Contingency 25%
H8130.20140 - H0229
1,095,555
Legal, Admin & Engineering 15%
H8130.20140 - H0229
657,333
MRB Design & Plan- 2024 Contract
H8130.40605 - H0229
(354,635)
Included below & in $657,333
2024 Contract
H8130.40605 - H0229
(26,625)
Included below & in $657,333
2024 Contract
H8130.40605 - H0229
(187,345)
Included below & in $657,333
MRB Construction Observation & Other Contract
H8130.40605 - H0229
(112,280)
Included below & in $657,333
23,552
Included below & in $657,333
MRB Estimated Project Cost
5,477,778
2021 Contract
H8130.40605 - H0229
38,000
MRB Design & Plan- 2024 Contract
H8130.40605 - H0229
354,635
2024 Contract
H8130.40605 - H0229
26,625
2024 Contract
H8130.40605 - H0229
187,345
MRB Construction Observation & Other Contract
H8130.40605 - H0229
112,280
Harris Beach
H8130.40605 - H0229
75,000
Municipal Solutions
H8130.40605 - H0229
43,337
Moody's
H8130.40605 - H0229
35,000
Legal & Administrative Costs
872,222
Total Estimated Expenditures
6,350,000