Town Board Meeting
Town Board Agenda 2025.04.03

Agenda

April 3, 2025 · 2 min read · extracted text · View original

Town Board Meeting Agenda

April 3, 2025 ~ 7:30 p.m.

Results

______________________________________________________________________________

Pledge of Allegiance ~ Roll Call

Open to the Floor

Each speaker will be allowed five minutes.

Minutes to be considered for approval: March 20, 2025 Agenda Approved

March 20, 2025 Meeting Approved

Regular Town Business:

1. Consideration to approve bills, as submitted by the Director of Finance.

Approved

2. Consideration to approve prepaid warrant as submitted by the Director of

Finance. Approved

3. Consideration to approve purchase orders as submitted by the Director of

Finance. Approved

4. Resolution to accept the 2024 Town of Webster Agreed Upon Procedures for

the Justice Accounts report dated March 24, 2025. Approved

5. Resolution to approve the Innovative Contracting Services (ICS), contract for

Phase 1 GIS Services and have the Supervisor sign said contract. Approved

6. Resolution to set a public hearing on May 1, 2025, on potential code changes

relating to code enforcement and to be published in the April 16, 2025, edition

of the Webster Herald. Approved*

Presentation

7. Resolution to set Public Hearing for May 1, 2025, to do an

amendment/corrective action to a PDD set up in 2019 on Ridge Commons and

publish said Public Hearing in the Wednesday, April 16, 2025, edition of the

Webster Herald. Approved

PDD Plan

8. Resolution to approve change order #3 for the Morsch Pipeline, Inc.

construction contract in regard to the Phillips to Tebor Road Conveyance Pipe

Project (H0237). The change order is to reroute the sewer for Monroe County

Water Authority, which is an additional cost of $76,868. Approved

Resolution

9. Resolution to approve change order #5 for the Morsch Pipeline, Inc.

construction contract in regard to the Phillips to Tebor Road Conveyance Pipe

Project (H0237). The change order is for ACP removal from section 1 to section

3 near Phillips Road which is an additional cost of $382,503.01. Approved

Resolution

9. Resolution to approve change order #5 for the Morsch Pipeline, Inc.

construction contract in regard to the Phillips to Tebor Road Conveyance Pipe

Project (H0237). The change order is for ACP removal from section 1 to section

3 near Phillips Road which is an additional cost of $382,503.01. Approved

Resolution

10. Resolution to authorize the Supervisor to sign an engineering and design

contract with MRB Group on the Vosburg Pump Station. Approved

This agenda is subject to change.

(*) Please note that the Public Hearing scheduled regarding potential code

changes relating to code enforcement (originally set April 3, 2025) will not be

taking place on May 1, 2025. We will post any updates on this hearing to our

website and in the Webster Herald. Thank you.

End of document