Town Board Workshop
Town Board Minutes 2025.07.03

Minutes

July 3, 2025 · 15 min read · extracted text · View original

Webster Town Board

July 3, 2025

A workshop meeting of the Webster Town Board was called to order by Supervisor Flaherty at

6:30 p.m. at the Webster Town Board Meeting Room, 1002 Ridge Road, Webster, New York,

with the following officials present:

Supervisor ................................................................................ Thomas J. Flaherty

Councilwoman ........................................................................... Patricia T. Cataldi

Councilman....................................................................................... John J. Cahill

Councilwoman ............................................................................ Ginny L. Nguyen

Councilwoman ...........................................................................Jennifer S. Wright

Attorney for the Town .................................................................... John DeMarco

Town Clerk .................................................................................. Danene M. Marr

Department Heads Present:

Town Engineer .............................................................................. Keith Mortimer

Police Chief ...............................................................................Dennis Kohlmeier

Parks and Recreation Director ............................................................ Chris Bilow

Finance Director ..................................................................................Paul Adams

Also in attendance was Maria Dewar, Administrative Assistant for the Director of Community

Planning and Development and the Town Engineer.

***

Keith Mortimer, Town Engineer, appeared before the Town Board to present the future animal

control and dog kennel/holding area options.

The Town is exploring options for a new or improved animal control and dog kennel holding

area due to changing state mandated requirements and loss of a sheltering partner. Mr. Mortimer

presents kenneling history from 2022 through June 2025, showing a small uptick in kenneling

needs. Mr. Mortimer highlights that typically the Town shelters one or two dogs at any given

time, though they’ve exceeded this capacity about four times during the reported period. He

notes the Town averages about six days of sheltering per dog.

Mr. Mortimer explains that about three and a half years ago, the Town’s partner, Pittsford

Animal Hospital, changed their business model and stopped providing sheltering operations.

The following timeline took place:

•

•

•

•

•

1

December 2023 - the Town applied for a $100,000.00 New York State Agriculture and

Markets Grant to build an estimated 1,000 square foot kennel/holding area.

January 2024 - the State Agriculture and Markets policies for the grant create an

estimated cost of the 1,100 square foot facility to be nearly $1 million.

February 2024 - the own applies for a $500,000.00 State Agriculture and Markets Grant.

Town’s estimated match is an estimated $600,000.00.

February 2025 - the Town receives State Agriculture and Markets award contract.

April 2024-June 2025 - the Town and design team assess alternatives to a $1 million

standalone kennel to achieve compliance with New York State Agriculture and Markets

while being less capital-intensive.

07-03-2025

Webster Town Board

He notes that while they received satisfactory compliance marks from New York State

Agriculture and Markets in both 2023 and 2024, the Town likely will not maintain compliance in

2025 due to ever changing requirements if the Town continues to maintain status quo.

Mr. Mortimer presented several upfront capital investment options with estimated construction

costs between $700,000.00 to $1.2 Million with four general population and one isolation area

for the dogs (Option A). Option one is a 1,100 square foot stand alone building at the

courthouse, with an estimated cost of $1 million ($400,000.00 grant, $600,000.00 Town match)

which could impact Park Land and/or wetlands. Option two is a 1,100 square foot stand-alone

building at Town Hall, with an estimated cost of $1 million ($400,000.00 grant, $600,000.00

Town match) which would impact Police Department parking. Option three is a 900 square foot

stand-alone building at Town Hall, with an estimated cost of $700,000.00 ($400,000.00 grant,

$300,000.00 Town match) this option would have no bathrooms, no offices, no storage and

would also impact the Police Department parking. Option four is a 1,300 square foot retrofit of

the old highway garage administration offices, with an estimated construction cost upwards to

$1.2 million ($400,000.00 in grant, $600,000.00-$800,000.00 Town match) this option would

require an amendment to the grant work plan, provides for expansion, dedicated exercise area,

and an opportunity for future intermunicipal revenue.

Mr. Mortimer then outlines non-capital options (Option B) that wouldn’t require the same

upfront investments. These include entering into an Intermunicipal Agreement (IMA) with

another Town, with early conversations showing interest from both Irondequoit and Penfield.

He notes this would require working out details for kenneling operations and would change the

process for residents reclaiming animals. Another option is contracting with a local kenneling

facilities like dog daycare businesses, though Mr. Mortimer notes limitations; these facilities

wouldn’t take dogs during the five-day holding period or accept dangerous dogs.

Dennis Kohlmeier, Webster Police Chief, provides historical context, noting that in 2021 the

animal control came back under police department purview, coinciding with the loss of their

sheltering contract. He commends the animal control officers for maintaining compliance

despite challenging conditions. From an operational perspective, the Chief explains that having

a local shelter under their control would be more efficient, allowing them to guarantee space and

make long-term housing arrangements. With an Intermunicipal Agreement, they would be at the

mercy of other organizations for space. The Chief notes their ideal goal is to have the kennel

centrally located at Town Hall for efficient reclamation processes but acknowledges that going

outside Town would have a heavier operational impact, potentially involving cost

reimbursements or additional staff. From a community perspective, the Town wants to provide

for a safe local holding area that facilitates an expeditious safe return of lost pets.

Councilwoman Cataldi asked about the number of dogs or the percentage of dogs that are housed

that people come to reclaim or if many of them are abandoned. Chief Kohlmeier responded

about 50 percent.

Councilman Cahill asked for clarification regarding the location of the kennel in the grant

application process. Chief Kohlmeier responded that the grant application indicated its location

to be at Town Hall.

2

07-03-2025

Webster Town Board

Councilwoman Wright reiterated that during the presentation it was stated that with the

Intermunicipal Agreements that space may not be guaranteed and asked if there are any other

municipalities that have these agreements and if there is a way to negotiate making sure that

there is at least a spot for two dogs for Webster at all times. Chief Kohlmeier responded that all

current facilities are reaching capacity and there is already a shuffle game and moving dogs to

another location. It is very much a first come first serve and has no guarantee of space.

Councilman Cahill added that they recently toured the Town of Irondequoit’s facility, and they

currently have five spaces with the capacity to add five more and they are willing to work with

us with respect to taking Webster dogs. From his perspective there are items that would need to

be worked out in an IMA and would not be as efficient as housing them here on the Town Hall

campus, but from a capital expenditure, we would save the taxpayers hundreds of thousands of

dollars and believe it would be worth looking into these IMA options further. Chief Kohlmeier

responded that a cost analysis of the life of the building has not been done to know whether the

personnel costs of an IMA would outweigh the capital expenses.

Supervisor Flaherty appreciated all of the great points the councilmembers brought up and wants

to make sure it is understood that Resolutions will need to be voted on at the July 17, 2025 Town

Board Meeting. The Town either needs to pursue an IMA or pursue a capital investment project,

because right now where we stand is untenable. The Police Department has been holding dogs

down in their area for two years now and the staff has tried to operate under what is less than

ideal circumstances.

Based on all extenuating circumstances of potentially going either the way of an Intermunicipal

Agreement or a Capital Investment Project, based on potential outcomes, we could be right back

in front of this Board with the problems that the team has run in to and that is just the reality of

this. Supervisor Flaherty states we need forward motion on this, and it cannot continue to be a

holding pattern.

Maria Dewar, Administrative Assistant, also added that it is imperative that we should make a

decision soon because the grant funding that the Town received has been in a holding pattern.

The Town has not signed the contract for five months and does not know if the State is going to

keep waiting while the Town makes a decision.

Following the presentation a general discussion took place.

***

Maria Dewar, Administrative Assistant for the Director of Community Planning and

Development and the Town Engineer, appeared before the Town Board to provide an insightful

presentation on tentative New York State Consolidated Funding Application (NYS CFA) for

grant strategy options. Several projects are aimed at improving Town infrastructure and

community services.

Ms. Dewar explains that NYS CFA allows participants, including municipalities like the Town

of Webster, to be considered for multiple sources of grant funding for a project by filling out just

one application.

3

07-03-2025

Webster Town Board

The first project outlined is for the Sandbar Park Phase 2 and 3 Design and Permitting. The

Local Waterfront Revitalization Program (LWRP) is a New York State Program that provides

financial assistance to eligible municipalities to prepare and implement strategies for community

and waterfront revitalization. The maximum award amount is $2,000,000.00 with the Town

match still being estimated. This grant requires a twenty-five percent match. The grant team

would include Town staff, and the grant writer would be Jean O’Connell and Associates.

The next project outlined is for the Geographical Information Systems (GIS) mapping and

Database Expansion. The non-Agricultural Nonpoint Source Planning and Municipal Separate

Storm Sewer System (MS4) Mapping Grant (NPG) is a comprehensive, reimbursement grant

program that funds planning reports for nonpoint source water quality improvement projects and

mapping of MS4 systems. The purpose of the grant would be to offset consultant fees for GIS

mapping and database expansion. The maximum award amount is $75,000.00 with the Town

requesting $75,000.00. This grant requires a ten percent match. The grant team and grant writer

would include Town staff closest to the project efforts.

The next project outlined is for the Town Recreation Center Improvements which is in part of

Village of Webster Reimagine Webster Project. The Brownfield Opportunity Area (BOA)

program is open to municipalities, targeting municipalities, community-based not-for-profit

organizations, and New York City Community Boards. The procurement focuses on four

distinct grant activities: Pre-Planning (area wide site identification and preliminary analysis),

Planning (developing or updating BOA Plans), Predevelopment Activities, and Phase II

Environmental Site Assessments for Brownfield sites. The purpose of the grant would be for

preliminary design for improvements to the Town Recreation Complex, including an

amphitheater, realigned driveway, new parking lot and shelter structure with restrooms. The

maximum award amount is $400,000.00 with the Town requesting $84,000.00. This grant

requires a ten percent match. The grant team would be Chris Bilow, Director of Parks and

Recreation and the grant writer is Webster Economic Development Alliance (WEDA).

The next project outlined is for the Highway Department Salt Barn Rebuild. The Water Quality

Improvement Project (WQIP) Program is a competitive, statewide reimbursement grant program

that funds projects that directly improve water quality or habitat, promote flood risk reduction,

restoration, and enhanced flood and climate resiliency, or protect a drinking water source.

During the review of available grant opportunities for the Highway Department Salt Barn, the

CFA WQIP grant seemed the best fit. There are two reasons for this: The grant period for this

award is May 19, 2025 to May 18, 2030. Expenses during this time period can be applied to the

grant. This allows the timeline of the Salt Barn to stay intact. Our grant consultant, Jean

O’Connell and Associates wrote the winning grant that was awarded to Orchard Park. The

maximum award amount is $600,000.00 with the Town requesting $600,000.00. This grant

requires a twenty-five percent match. The grant team would include Town staff closest to the

project efforts and the grant writer would be Jean O’Connell and Associates.

The next project outlined is for the Vosburg Pump Station. The Water Quality Improvement

Project (WQIP) program is a competitive, statewide reimbursement grant program that funds

projects that directly improve water quality or habitat, promote flood risk reduction, restoration,

and enhanced flood and climate resiliency, or protect a drinking water source. The Vosburg

Pump Station equipment is well past its life span and this station receives a large amount of flow.

4

07-03-2025

Webster Town Board

The purpose of the grant is to rehabilitate the Vosburg Pump Station, including modernization

and upgrades. The maximum award amount is seventy-five percent of construction with the

Town requesting an estimate of $2,671,875 (estimate is based on $5.7 million bonded in 2024).

This grant requires a twenty-five percent match. The grant team would include Town staff

closest to the project efforts and the grant writer would be MRG Group.

The last project outlined is for the Shipbuilders Creek Restoration Project. The Water Quality

Improvement Project (WQIP) Program is a competitive, statewide reimbursement grant program

that funds projects that directly improve water quality or habitat, promote flood risk reduction,

restoration, and enhanced flood and climate resiliency, or protect a drinking water source.

Shipbuilders Creek is an identified impaired water source and sewer infrastructure needs to be

replaced due to erosion of the creek bank. Additionally, there has been a previous failure, and

the Sewer Department is currently in the process of an intermediate remedy for the highest

priority infrastructure. The purpose of this grant is to Restore the east branch of Shipbuilders

Creek. The maximum award amount is $15,000,000.00 with the Town requesting $872,000.00.

This project requires a twenty-five percent match. The grant team would include Town staff

closest to the project efforts and the grant writer would be Barton & Loguidice.

Ms. Dewar emphasized the need for the Town Board to vote on the proposed Resolutions to

move forward with the grant applications. Without Board approval, the Town cannot proceed

with the applications, which are crucial for securing funding for these projects.

Following the presentation a general discussion took place.

***

There being no further business to come before the Board, the meeting was adjourned at

7:19 p.m.

____________________________________

Danene M. Marr, Town Clerk

5

07-03-2025

End of document