Town Board Workshop
Town Board Minutes 2025.11.06

Minutes

November 6, 2025 · 15 min read · extracted text · View original

Webster Town Board

November 6, 2025

A workshop meeting of the Webster Town Board was called to order by Supervisor Flaherty at

6:00 p.m. at the Webster Town Board Meeting Room, 1002 Ridge Road, Webster, New York,

with the following officials present:

Supervisor ................................................................................ Thomas J. Flaherty

Councilwoman ........................................................................... Patricia T. Cataldi

Councilman....................................................................................... John J. Cahill

Councilwoman ............................................................................ Ginny L. Nguyen

Councilwoman...........................................................................Jennifer S. Wright

Attorney for the Town .........................................................................Kyle Taylor

Town Clerk .................................................................................. Danene M. Marr

Department Heads Present:

Community Development Director ..................................................... Josh Artuso

Finance Director ..................................................................................Paul Adams

Highway Superintendent ................................................................... Pat Stephens

Parks and Recreation Director .............................................................Chris Bilow

Also in attendance was Rick Kenealy, Wastewater Treatment Plant Chief Operator.

***

Josh Artuso, Community Development Director, appeared before the Town Board to present the

Transportation Alternatives Program (TAP) Grant application for sidewalks in West Webster

Hamlet. The presentation began with a recap of revitalization efforts in the West Webster area,

highlighting key milestones over the past five years. The Webster Economic Development

Alliance (WEDA) secured a $90,000 grant in 2021 to conduct a community-led planning study,

which was finalized in June 2023. Priority recommendations focused on improving the

intersection of Old Ridge and Gravel Roads, addressing blighted properties, and adding

streetscape enhancements, including sidewalks, lighting, and signage. Community input

emphasized pedestrian safety and the removal of blighting influences, which led to the

demolition of the former Webster Furniture Stripper building in August 2025, generating

renewed interest and investment in the area.

The Transportation Alternatives Program (TAP) Grant was introduced as a funding source to

improve pedestrian and bicycle infrastructure, support safe routes to schools, and encourage nonmotorized travel. Eligible projects include planning, design, and construction of sidewalks and

bicycle facilities, with a maximum federal reimbursement of 80% and a 20% local match. The

Town had previously used TAP funding to construct sidewalks on Ridge Road and applied

unsuccessfully in 2023 for West Webster improvements. Feedback from the 2023 debrief

suggested including survey and preliminary design work to strengthen future applications.

To prepare for a competitive TAP application, the Town solicited proposals from three

engineering firms for survey and preliminary design services. Two levels of service were

considered: a basic survey of the right-of-way and a more comprehensive preliminary design that

would identify sidewalk alignments, obstructions, drainage issues, and easement requirements, as

well as include public and internal meetings. Costs for these services ranged from $15,000 for

survey-only work to $36,000–$80,000 for preliminary design. Town staff recommended Costich

Engineering’s preliminary design proposal at $36,000, which includes survey work.

1

11-06-2025

Webster Town Board

The Board discussed timing, scope, and funding. The survey and preliminary design would

position the Town to submit a strong TAP Grant Application in 2026, potentially covering 80%

of project costs. While the TAP portal has not officially opened, the intent is to have the work

completed before the application deadline. Even if the grant is not awarded, the survey work

would provide the Town with valuable information about utilities and infrastructure along Old

Ridge. The project would be funded from the General Part-Town B Fund surplus, not the 2026

budget.

Board members raised questions about project length, reimbursement timelines, and coordination

with the ongoing comprehensive plan. Mr. Artuso confirmed that the West Webster Hamlet

sidewalk project spans approximately 1.1 miles, with potential expansions not included in the

current proposal. The preliminary design would strengthen the grant application, especially with

recent income survey data that demonstrates low-to-moderate income levels in the area. The

consensus emphasized moving forward with survey and design services now to maintain

momentum in revitalizing the West Webster Hamlet and to ensure competitive positioning for

future grant funding.

***

Pat Stephens, Highway Superintendent, appeared before the Town Board to present the Salt

Barn/Wash Station process, timeline, and updated estimated costs including demolition of the old

garage. The project maintains the original scope, with no changes, and involves constructing a

new salt barn with increased capacity, demolishing the current highway garage, and adding a

standalone truck washout building to meet Environmental Protection Agency (EPA)

recommendations and improve water quality. The plans are now 100% complete, though cost

estimates initially based on 60% design plans have risen due to project complexities.

Key costs include $1.9 million for the salt barn, $1.6 million for the truck washout building,

$950,000 for demolition, and $1.4 million for paving and utilities. Additional budget

considerations cover incidental expenses, design, insurance, legal fees, and a $350,000

construction contingency. Potential cost savings of roughly $2 million could bring the total

estimated project cost to $4.7 million.

Several cost-saving strategies were outlined. These include a $600,000 State Grant related to

water quality, $300,000 from existing state CHIP funding, an alternative to use timber frame

push walls instead of concrete in the salt barn, and self-performance of certain paving and utility

tasks by the Highway Department, potentially saving $825,000. Competitive bidding could

further reduce costs.

Comparing the current estimates to those presented in February, the earlier numbers were based

on generic per-square-foot pricing and proved conservative. The finalized design revealed

additional complexities, particularly regarding exterior utilities, increasing costs. However,

transitioning from 60% to 100% plans is not expected to significantly change the estimates.

The project remains under the current approved bond allocation of $21 million for the highway

building and related additions, with the salt barn portion projected to leave roughly $1.88 million

under the approved budget. Replacing the existing salt building is urgent due to structural

deterioration and insufficient storage capacity, which could jeopardize winter road safety and

limit salt availability during high-demand periods.

2

11-06-2025

Webster Town Board

The truck washout building is integral to the grant application, which may influence phasing

decisions to minimize upfront costs. Next steps involve preparing bid documents, analyzing

bids, and potentially awarding construction contracts. Splitting the project into multiple RFPs

could require additional effort and minor costs but may allow more targeted bidding and

scheduling flexibility.

Questions from Board members addressed the feasibility of self-performing certain tasks, the

structural integrity of the current salt barn, and potential use of the General Fund to offset project

costs. The presentation confirmed the building has a limited remaining lifespan and highlighted

the urgency of replacement while acknowledging grant outcomes expected in December could

impact timing.

Finally, Board members discussed procedural considerations, including bid timelines and the

ability to reject bids that exceed budget estimates. Splitting the project into separate RFPs would

alter the timeline and potentially increase consultant costs slightly, but overall, the plan remains

feasible within the current bond and funding structure, ensuring safe and reliable highway

operations.

***

Chris Bilow, Parks and Recreation Director, appeared before the Town Board to present on

Sandbar Park storage container and bid process. The presentation focused on exploring the

concept of modular storage container facilities at Sandbar Park, intended to operate seasonally as

food and beverage services. The goal is to move forward with a bid process to gather concrete

cost data for the Town Board, allowing them to make an informed decision about whether to

proceed with the project. The plan involves two containers: a 40-foot unit for a restaurant and a

20-foot unit for a bar, both equipped with basic infrastructure like stove vent hoods, fire

suppression systems, grease traps, and utility connections. Operators would be responsible for

outfitting these containers with their own equipment.

The bid process is expected to produce results by mid-December, with the Town Board

reviewing the costs and deciding whether to continue pursuing the project. If bids are favorable,

the Town would solicit proposals from potential operators, including traditional restaurant

owners and seasonal food truck vendors, aiming to secure an operator for the 2026 season. The

acceptance of the low bid and selection of an operator would likely occur in early 2026, giving

sufficient time to ensure the project’s feasibility and operational readiness.

Concerns from previous discussions about downsizing a brick-and-mortar restaurant were

addressed, highlighting that smaller buildings are not viable for profitability or bond repayment.

A modular container approach, potentially funded through the parkland trust fund instead of

bonds, would create a more financially sustainable model for operators and simplify negotiations

with the town. The infrastructure of the containers would be standardized to meet county health

and safety requirements while allowing flexibility for operators to outfit them to their needs.

Conceptual designs were developed to illustrate the layout of the containers, with the 40-foot

restaurant positioned on the north side of the park and the 20-foot bar on the east. The designs

also include features like a small stage, outdoor seating, fire pits, patio heaters, and recreational

opportunities, allowing operators to enhance the visitor experience. These conceptual visuals

help provide context for evaluating costs, feasibility, and operational logistics before making

final decisions.

3

11-06-2025

Webster Town Board

The discussion emphasized the importance of relying on actual bid data rather than theoretical

projections to guide decision-making. Board members noted that gathering cost information is

crucial for determining whether the project is financially viable. Additionally, the process

involves ongoing consultation with potential operators to understand their needs, ensuring that

the containers provide the necessary infrastructure while leaving the final outfitting to the

operators themselves.

Finally, the timeline and decision-making process were outlined. A Resolution to put the project

out to bid would occur first, with bids reviewed in mid-December. If costs are reasonable, a

Request for Proposal (RFP) would be issued to potential operators, and by late January or

February, the Town Board would decide whether to accept a bid and move forward with a

selected operator. This phase approach mitigates financial risk while gathering the essential data

needed to evaluate the project’s feasibility for the 2026 season.

***

Lynn Mucenski-Keck, representative from Withum, appeared before the Town Board to present

the results of the Withum report on Dewer Renewable Natural Gas (RNG) Project. Ms.

Mucenski-Keck opened by introducing herself and her role at the National Tech Service Group,

where she focuses on clean energy and legislative matters. She explained that her team works

with both for-profit and non-profit organizations to maximize investments in clean energy

projects, particularly under the Inflation Reduction Act. She noted her firm’s recent expansion

into upstate New York, including Buffalo, Rochester, and Batavia, which led to their

engagement with the Town of Webster.

The main topic of her presentation was the biogas property connected to Webster’s waste

recovery system. She clarified that she is not an engineer but explained the process: methane

from waste can be processed through a biogas system to produce natural gas. Webster’s system

already uses a portion of the gas, and she discussed opportunities to use the remaining gas for

sale, instead of flaring it, which benefits both the environment and the Town financially.

A key point of her presentation was the importance of starting construction on the biogas project

before December 31, 2024. This timing ensures eligibility for federal tax credits under the

Inflation Reduction Act, which now allows not-for-profits and governmental organizations to

receive refundable credits—a significant shift from prior law. She explained that the credit could

cover 30% of eligible project costs, though recapture rules apply if the project is discontinued

within five years.

Ms. Mucenski-Keck outlined the 5% safe harbor rule, which requires a minimum of 5% of

project costs to be spent before the end of 2024 to qualify for the tax credit. For Webster’s

project, $3.5 million was already spent, exceeding the safe harbor threshold. She also discussed

the continuity requirement, ensuring the project is completed within four years of starting, with

Webster’s project contracted with Navitas and expected to be in service by December 31, 2027.

The potential Investment Tax Credit (ITC) range was presented conservatively, with an initial

estimate of $33.4 million in eligible costs, resulting in an ITC refund of $8–10 million. After

accounting for municipal bond limitations and grants, the realistic net credit was projected at $7–

8.5 million. She emphasized the conservative approach to avoid IRS scrutiny and highlighted

that the final memo contains a detailed 14-page analysis.

4

11-06-2025

Webster Town Board

Finally, Ms. Mucenski-Keck addressed questions from the Town Board, confirming the stability

of incentives under current legislation and the potential for additional revenue from renewable

natural gas. She reiterated that the presentation was informational only, with no Resolutions

being voted on that evening. The next steps include presentations on financial and engineering

costs at upcoming workshops.

There being no further business to come before the Board, the meeting was adjourned at

7:30 p.m.

____________________________________

Danene M. Marr, Town Clerk

5

11-06-2025

End of document