Effect of Renewable Natural Gas Investment Tax Credit on Wastewater Treatment Plant Project November 20, 2025

2

POTENTIAL RNG INVESTMENT TAX CREDIT RANGE

Results per Withum, Smith & Brown, P.C. Safe Harbor CPA Memo

Total RNG ITC Basis Eligible for the Tax Credit Qualified Applicable Percentage per the IRS Projected Gross RNG ITC Credit Reduction for Municipal Tax Exempt Financing - 15% Projected Net RNG ITC Credit

WITH MIN ITC

WITH MAX ITC

26,752,993

33,441,242

30%

30%

8,025,898

10,032,373

(1,203,885)

(1,504,856)

6,822,013

8,527,517

3 ORIGINAL WWTP PROJECT VS. RNG PROJECT Below is a comparison of the expected serial bond borrowing for the current project vs. the RNG project at the minimum and maximum ITC credit amounts: NO ITC

WITH MAX ITC

WITH MIN ITC

Original Project Per 9/5/24 Bond Resolution

Projected Financial Results with RNG Maximum ITC

Projected Financial Results with RNG Minimum ITC

Expected Project Cost

87,000,000

96,000,000

96,000,000

Proceeds from WEDA Grant

(20,000,000)

(20,000,000)

(20,000,000)

0

(8,527,517)

(6,822,013)

67,000,000

67,472,483

69,177,987

DESCRIPTION

Projected RNG Investment Tax Credit from the IRS Net Amount to be Borrowed via Serial Bonds

4 PROJECTED IMPACT ON TOWN FINANCIAL STATEMENTS Below is a comparison of the expected annual cost for the current project vs. the RNG project at the minimum and maximum ITC credit amounts. The RNG project will result in an annual savings of $353,000 to $428,000.

NO ITC Original Project Per 9/5/24 Bond Resolution

WITH MAX ITC Projected Financial Results with RNG Maximum ITC

WITH MIN ITC Projected Financial Results with RNG Minimum ITC

4,020,000

4,048,000

4,151,000

Revenue

Sale of Pipeline Quality Natural Gas

0

(506,000)

(506,000)

Renewable Natural Gas Processing Cost

0

50,000

50,000

Projected Net Annual Cost of Capital Project

4,020,000

3,592,000

3,695,000

428,000

353,000

DESCRIPTION Annual Debt Service Cost

Principal & Interest

Net Annual Cost Savings from Current Capital Project

5 DEBT SERVICE VALUE OF SAVINGS FROM RNG PROJECT Each $1,000,000 of funds borrowed equates to $60,000 per year in debt service costs. Therefore, the RNG tax credit savings of $353,000 to $428,000 is equivalent to a reduction in borrowing of $5,883,000 to $7,133,000. This will go a long way toward funding the Vosburg Road Pump Station project or fulfilling other needs within the sewer system.

Net Annual Cost Savings from Current Capital Project Debt Service Value of Net Annual Cost Savings

WITH MAX ITC

WITH MIN ITC

428,000

353,000

7,133,000

5,883,000

6

Town of Webster Effect of Renewable Natural Gas Investment Tax Credit on Wastewater Treatment Plant Project

Questions and Comments