Attachment 1 Coca Cola/ Fairlife® Development Project

Proposed Additional Services Fee Schedule Prepared for Town of Webster December 18, 2025

I. Project Coordinator Involvement Based on the Request for additional Project Coordinator services, our proposed staffing and compensation, detailed below, assumes 62 hrs/mo for Project lead/Coordinator services, 24 hrs/mo for Project Coordinator services, and 4 hrs/Mo for Project Administrative services to be provided through December 2026 (or when Certificate of Occupancy is issued, if sooner). A salary schedule inclusive of the Project Coordinator and additional support staff, if required, is detailed below.

II. 2026 Salary Schedule for Project Coordinator Services (includes rates for addititional support staff available to be provided, if required)

Hourly Rate*

Staffing Level / Role

$ 220 $ 190 $ 140 $ 130 $ 135 $ 120 $ 135 $ 135 $ 80 * inclusive of overhead

Vice President In-Charge Project Executive Senior Project Manager Project Manager/Coordinator Senior Field Manager Field Manager Director of Project Development Chief Estimator Administrative Assistant

III. Staffing Table Total Months

Staffing Level / Role

Anticipated Tasks

Jared Miller Project Executive

Provide leadership and attend project meetings as needed for coordination of activities Provide project coordination, scheduling, administration, and representation as Project Coordinator on the Town's behalf Provide project coordination, scheduling, administration, and representation as Project Coordinator on the Town's behalf

Rory Fitzpatrick (Project Lead) Project Coordinator Daniel Andrews Project Coordinator Holly Rickard Administrative Assistant

12

Total Hours

12

IV. Non-Salary Costs (for budgeting purposes only)

Hourly Rate

Estimated Salary Costs

As Needed

$

190

$

0

62

$

130

$

96,720

24

$

130

$

37,440

4

$

80

$

3,840

$

138,000

1,080

Preparation of meeting minutes, Organization of the projects online database.

Staffing Subtotals

Staff Delegation (Hrs/Mo)

1,080

90

Estimated Lump

Description

$ $ $ $ $ $ $ $ $

Cellular Telephones Office Supplies Computers/Licenses Printers Miscellaneous Reproduction (Drawings & Specs.) Postage/UPS/Federal Express Contingency Software Monthly License

Non-Salary Costs Subtotal

V. Summary (Project Coordinator Services Lump Sum Cost)

Compensation

$ $ $

Total Staffing Salary Costs Total Non-Salary Costs

Total Fixed Fee

0 0 0 0 0 0 0 0 0

Totals

138,000 0 138,000

These amounts include all costs associated with our project service, including staff salaries, benefits, insurance, travel, and contribution to corporate overhead and profit. If the Town is in agreement, please sign below and return one (1) copy to Campus Construction Management Group Inc. at your earliest convenience. Upon acceptance, a contract amendment will be submitted for your review and approval.

Thomas Flaherty, Town Supervisor Town of Webster

Date

Mark Esposito, President Campus Construction Management Group, Inc.

12/18/2025 Date